Elmora construction progress

The registered completion date for Elmora in Jumeirah Garden City is February 2028. At the last site inspection, in November 2026, it was 3.9% built. The developer is Neoterra Real Estate Development.

3.9%

Built, at the site inspection of 17 November 2026

Running behind its date

Registered completion date
February 2028
Finish at recent pace
March 2040
Construction started
December 2025
First registered
October 2025
Developer
Neoterra Real Estate Development
Units
85
Escrow bank
The National Bank of Fujairah
Name in Arabic
المورا
Project number
4088
Site inspections
3

Schedule

Between May 2026 and November 2026 the site added about 0.6 points a month. At that rate it would finish around March 2040, more than three months after its registered date of February 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 November 2026

3.9%+3.8 pts

  • Elmora construction site, inspection photo 1, 17 November 2026
  • Elmora construction site, inspection photo 2, 17 November 2026
  • Elmora construction site, inspection photo 3, 17 November 2026
  • Elmora construction site, inspection photo 4, 17 November 2026

7 May 2026

0%+0.0 pts

  • Elmora construction site, inspection photo 1, 7 May 2026
  • Elmora construction site, inspection photo 2, 7 May 2026
  • Elmora construction site, inspection photo 3, 7 May 2026

17 September 2025

0%

  • Elmora construction site, inspection photo 1, 17 September 2025
  • Elmora construction site, inspection photo 2, 17 September 2025

All 10 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Own a unit in Elmora?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elmora handover date?
The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elmora?
Elmora was 3.9% built at the site inspection on 17 November 2026. The site has been inspected 3 times since September 2025. The Land Department took 10 site photos at its inspections.
Is Elmora delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Elmora?
The registered developer is Neoterra Real Estate Development.
Which bank holds the escrow account for Elmora?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.