Enso Jade construction progress
Enso Jade in Jumeirah Garden City was registered to complete in June 2026 and is still under construction. At the last site inspection, in July 2026, it was 42% built. The developer is Enso Development.
42%
Built, at the site inspection of 14 July 2026
5 months past its registered completion date
- Registered completion date
- June 2026
- Finish at recent pace
- January 2028
- Construction started
- September 2024
- First registered
- October 2024
- Developer
- Enso Development
- Community
- Jumeirah Garden City
- Units
- 105
- Escrow bank
- Mashreq Bank
- Name in Arabic
- إنسو جاد
- Project number
- 3249
- Site inspections
- 6
Schedule
Enso Jade was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around January 2028.
Site inspections
14 July 2026
42%+8.3 pts
13 April 2026
34%+12 pts
8 January 2026
21%+7.7 pts
20 October 2025
14%+5.5 pts
9 June 2025
8.1%+8.1 pts
12 September 2024
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Enso Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Enso Jade?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Enso Jade handover date?
- The registered completion date was June 2026, and the register still lists Enso Jade as under construction. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Enso Jade?
- Enso Jade was 42% built at the site inspection on 14 July 2026. The site has been inspected 6 times since September 2024. The Land Department took 33 site photos at its inspections.
- Is Enso Jade delayed?
- Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
- Who is building Enso Jade?
- The registered developer is Enso Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Enso Jade?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Enso AmberAlso by Enso Development. 11%, Due June 2026, passed.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)