Enso Jade construction progress

Enso Jade in Jumeirah Garden City was registered to complete in June 2026 and is still under construction. At the last site inspection, in July 2026, it was 42% built. The developer is Enso Development.

42%

Built, at the site inspection of 14 July 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
January 2028
Construction started
September 2024
First registered
October 2024
Developer
Enso Development
Units
105
Escrow bank
Mashreq Bank
Name in Arabic
إنسو جاد
Project number
3249
Site inspections
6

Schedule

Enso Jade was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around January 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 July 2026

42%+8.3 pts

  • Enso Jade construction site, inspection photo 1, 14 July 2026
  • Enso Jade construction site, inspection photo 2, 14 July 2026
  • Enso Jade construction site, inspection photo 3, 14 July 2026
  • Enso Jade construction site, inspection photo 4, 14 July 2026

13 April 2026

34%+12 pts

  • Enso Jade construction site, inspection photo 1, 13 April 2026
  • Enso Jade construction site, inspection photo 2, 13 April 2026
  • Enso Jade construction site, inspection photo 3, 13 April 2026
  • Enso Jade construction site, inspection photo 4, 13 April 2026

8 January 2026

21%+7.7 pts

  • Enso Jade construction site, inspection photo 1, 8 January 2026
  • Enso Jade construction site, inspection photo 2, 8 January 2026
  • Enso Jade construction site, inspection photo 3, 8 January 2026
  • Enso Jade construction site, inspection photo 4, 8 January 2026

20 October 2025

14%+5.5 pts

  • Enso Jade construction site, inspection photo 1, 20 October 2025
  • Enso Jade construction site, inspection photo 2, 20 October 2025
  • Enso Jade construction site, inspection photo 3, 20 October 2025
  • Enso Jade construction site, inspection photo 4, 20 October 2025

9 June 2025

8.1%+8.1 pts

  • Enso Jade construction site, inspection photo 1, 9 June 2025
  • Enso Jade construction site, inspection photo 2, 9 June 2025
  • Enso Jade construction site, inspection photo 3, 9 June 2025
  • Enso Jade construction site, inspection photo 4, 9 June 2025

12 September 2024

0%

  • Enso Jade construction site, inspection photo 1, 12 September 2024
  • Enso Jade construction site, inspection photo 2, 12 September 2024

All 33 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Enso Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Enso Jade?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Enso Jade handover date?
The registered completion date was June 2026, and the register still lists Enso Jade as under construction. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Enso Jade?
Enso Jade was 42% built at the site inspection on 14 July 2026. The site has been inspected 6 times since September 2024. The Land Department took 33 site photos at its inspections.
Is Enso Jade delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Enso Jade?
The registered developer is Enso Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Enso Jade?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.