Onaya Residences By Kaya construction progress
Onaya Residences By Kaya in Jumeirah Garden City is 38% built at the Land Department inspection of February 2026. Developer Kaya Properties. Completion registered for June 2026.
38%
Built, at the Land Department site inspection of 19 February 2026
4 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- January 2028
- Construction started
- November 2024
- Registered with the Land Department
- February 2026
- Developer
- Kaya Properties
- Community
- Jumeirah Garden City
- Units
- 41
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- اونايا ريزيدنسز باي كايا
- Land Department project number
- 3565
- Land Department site inspections
- 2
Schedule
Onaya Residences By Kaya was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around January 2028.
Site inspections
19 February 2026
38%+30 pts
11 March 2025
7.5%
Context
Jumeirah Garden City has 27 projects under construction, 30% built on average.
Own a unit in Onaya Residences By Kaya?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Onaya Residences By Kaya be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around January 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Onaya Residences By Kaya is built?
- 38%, measured at the Land Department site inspection on 19 February 2026. The Land Department engineers have inspected the site 2 times since March 2025.
- Is Onaya Residences By Kaya delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Onaya Residences By Kaya?
- The registered developer is Kaya Properties.
- Which bank holds the escrow account for Onaya Residences By Kaya?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The GrandalaNearby in Jumeirah Garden City. 86%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 31%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.