Skip to content

Onaya Residences By Kaya construction progress

Onaya Residences By Kaya in Jumeirah Garden City is 38% built at the Land Department inspection of February 2026. Developer Kaya Properties. Completion registered for June 2026.

38%

Built, at the Land Department site inspection of 19 February 2026

4 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
January 2028
Construction started
November 2024
Registered with the Land Department
February 2026
Developer
Kaya Properties
Units
41
Escrow bank
Emirates Islamic Bank
Name in Arabic
اونايا ريزيدنسز باي كايا
Land Department project number
3565
Land Department site inspections
2

Schedule

Onaya Residences By Kaya was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around January 2028.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 February 2026

38%+30 pts

  • Onaya Residences By Kaya construction site, Land Department inspection photo 1, 19 February 2026
  • Onaya Residences By Kaya construction site, Land Department inspection photo 2, 19 February 2026
  • Onaya Residences By Kaya construction site, Land Department inspection photo 3, 19 February 2026
  • Onaya Residences By Kaya construction site, Land Department inspection photo 4, 19 February 2026

11 March 2025

7.5%

  • Onaya Residences By Kaya construction site, Land Department inspection photo 1, 11 March 2025
  • Onaya Residences By Kaya construction site, Land Department inspection photo 2, 11 March 2025
  • Onaya Residences By Kaya construction site, Land Department inspection photo 3, 11 March 2025
  • Onaya Residences By Kaya construction site, Land Department inspection photo 4, 11 March 2025

All 11 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Own a unit in Onaya Residences By Kaya?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Onaya Residences By Kaya be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around January 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Onaya Residences By Kaya is built?
38%, measured at the Land Department site inspection on 19 February 2026. The Land Department engineers have inspected the site 2 times since March 2025.
Is Onaya Residences By Kaya delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Onaya Residences By Kaya?
The registered developer is Kaya Properties.
Which bank holds the escrow account for Onaya Residences By Kaya?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.