Onaya Residences By Kaya construction progress

Onaya Residences By Kaya in Jumeirah Garden City was registered to complete in June 2026 and is still under construction. At the last site inspection, in February 2026, it was 38% built. The developer is Kaya Properties.

38%

Built, at the site inspection of 19 February 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
January 2028
Construction started
November 2024
First registered
February 2026
Developer
Kaya Properties
Units
41
Escrow bank
Emirates Islamic Bank
Name in Arabic
اونايا ريزيدنسز باي كايا
Project number
3565
Site inspections
2

Schedule

Onaya Residences By Kaya was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around January 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 February 2026

38%+30 pts

  • Onaya Residences By Kaya construction site, inspection photo 1, 19 February 2026
  • Onaya Residences By Kaya construction site, inspection photo 2, 19 February 2026
  • Onaya Residences By Kaya construction site, inspection photo 3, 19 February 2026
  • Onaya Residences By Kaya construction site, inspection photo 4, 19 February 2026

11 March 2025

7.5%

  • Onaya Residences By Kaya construction site, inspection photo 1, 11 March 2025
  • Onaya Residences By Kaya construction site, inspection photo 2, 11 March 2025
  • Onaya Residences By Kaya construction site, inspection photo 3, 11 March 2025
  • Onaya Residences By Kaya construction site, inspection photo 4, 11 March 2025

All 11 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Own a unit in Onaya Residences By Kaya?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Onaya Residences By Kaya handover date?
The registered completion date was June 2026, and the register still lists Onaya Residences By Kaya as under construction. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Onaya Residences By Kaya?
Onaya Residences By Kaya was 38% built at the site inspection on 19 February 2026. The site has been inspected 2 times since March 2025. The Land Department took 11 site photos at its inspections.
Is Onaya Residences By Kaya delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Onaya Residences By Kaya?
The registered developer is Kaya Properties.
Which bank holds the escrow account for Onaya Residences By Kaya?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.