171 Garden Heights construction progress

The registered completion date for 171 Garden Heights in Jumeirah Garden City is December 2026. At the last site inspection, in June 2026, it was 34% built. The developer is Jad Global Real Estate Development.

34%

Built, at the site inspection of 8 June 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
August 2028
Construction started
September 2024
First registered
September 2024
Units
159
Escrow bank
Dubai Islamic Bank
Name in Arabic
171 جاردن هايتس
Project number
3127
Site inspections
6

Schedule

Between July 2025 and June 2026 the site added about 2.5 points a month. At that rate it would finish around August 2028, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 June 2026

34%+7.4 pts

  • 171 Garden Heights construction site, inspection photo 1, 8 June 2026
  • 171 Garden Heights construction site, inspection photo 2, 8 June 2026
  • 171 Garden Heights construction site, inspection photo 3, 8 June 2026
  • 171 Garden Heights construction site, inspection photo 4, 8 June 2026

24 February 2026

26%+12 pts

  • 171 Garden Heights construction site, inspection photo 1, 24 February 2026
  • 171 Garden Heights construction site, inspection photo 2, 24 February 2026
  • 171 Garden Heights construction site, inspection photo 3, 24 February 2026
  • 171 Garden Heights construction site, inspection photo 4, 24 February 2026

12 November 2025

14%+7.6 pts

  • 171 Garden Heights construction site, inspection photo 1, 12 November 2025
  • 171 Garden Heights construction site, inspection photo 2, 12 November 2025
  • 171 Garden Heights construction site, inspection photo 3, 12 November 2025
  • 171 Garden Heights construction site, inspection photo 4, 12 November 2025

16 July 2025

6.7%+2.8 pts

  • 171 Garden Heights construction site, inspection photo 1, 16 July 2025
  • 171 Garden Heights construction site, inspection photo 2, 16 July 2025
  • 171 Garden Heights construction site, inspection photo 3, 16 July 2025
  • 171 Garden Heights construction site, inspection photo 4, 16 July 2025

2 April 2025

4.0%+4.0 pts

  • 171 Garden Heights construction site, inspection photo 1, 2 April 2025
  • 171 Garden Heights construction site, inspection photo 2, 2 April 2025
  • 171 Garden Heights construction site, inspection photo 3, 2 April 2025
  • 171 Garden Heights construction site, inspection photo 4, 2 April 2025

19 June 2024

0%

  • 171 Garden Heights construction site, inspection photo 1, 19 June 2024

All 34 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Jad Global Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in 171 Garden Heights?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the 171 Garden Heights handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on 171 Garden Heights?
171 Garden Heights was 34% built at the site inspection on 8 June 2026. The site has been inspected 6 times since June 2024. The Land Department took 34 site photos at its inspections.
Is 171 Garden Heights delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building 171 Garden Heights?
The registered developer is Jad Global Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for 171 Garden Heights?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.