171 Garden Heights construction progress
The registered completion date for 171 Garden Heights in Jumeirah Garden City is December 2026. At the last site inspection, in June 2026, it was 34% built. The developer is Jad Global Real Estate Development.
34%
Built, at the site inspection of 8 June 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- August 2028
- Construction started
- September 2024
- First registered
- September 2024
- Developer
- Jad Global Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 159
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- 171 جاردن هايتس
- Project number
- 3127
- Site inspections
- 6
Schedule
Between July 2025 and June 2026 the site added about 2.5 points a month. At that rate it would finish around August 2028, more than three months after its registered date of December 2026.
Site inspections
8 June 2026
34%+7.4 pts
24 February 2026
26%+12 pts
12 November 2025
14%+7.6 pts
16 July 2025
6.7%+2.8 pts
2 April 2025
4.0%+4.0 pts
19 June 2024
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Jad Global Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in 171 Garden Heights?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 171 Garden Heights handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 171 Garden Heights?
- 171 Garden Heights was 34% built at the site inspection on 8 June 2026. The site has been inspected 6 times since June 2024. The Land Department took 34 site photos at its inspections.
- Is 171 Garden Heights delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building 171 Garden Heights?
- The registered developer is Jad Global Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for 171 Garden Heights?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Jad 288Also by Jad Global Real Estate Development. 1.9%, Due December 2027.
- J188Also by Jad Global Real Estate Development. 0%, Due April 2028.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.