171 Garden Heights construction progress

171 Garden Heights in Jumeirah Garden City is 34% built at the Land Department inspection of June 2026. Developer Jad Global Real Estate Development. Completion registered for December 2026.

34%

Built, at the Land Department site inspection of 8 June 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
August 2028
Construction started
September 2024
Registered with the Land Department
September 2024
Units
159
Escrow bank
Dubai Islamic Bank
Name in Arabic
171 جاردن هايتس
Land Department project number
3127
Land Department site inspections
6

Schedule

Between July 2025 and June 2026 the site added about 2.5 points a month. At that rate it would finish around August 2028, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

8 June 2026

34%+7.4 pts

  • 171 Garden Heights construction site, Land Department inspection photo 1, 8 June 2026
  • 171 Garden Heights construction site, Land Department inspection photo 2, 8 June 2026
  • 171 Garden Heights construction site, Land Department inspection photo 3, 8 June 2026
  • 171 Garden Heights construction site, Land Department inspection photo 4, 8 June 2026

24 February 2026

26%+12 pts

  • 171 Garden Heights construction site, Land Department inspection photo 1, 24 February 2026
  • 171 Garden Heights construction site, Land Department inspection photo 2, 24 February 2026
  • 171 Garden Heights construction site, Land Department inspection photo 3, 24 February 2026
  • 171 Garden Heights construction site, Land Department inspection photo 4, 24 February 2026

12 November 2025

14%+7.6 pts

  • 171 Garden Heights construction site, Land Department inspection photo 1, 12 November 2025
  • 171 Garden Heights construction site, Land Department inspection photo 2, 12 November 2025
  • 171 Garden Heights construction site, Land Department inspection photo 3, 12 November 2025
  • 171 Garden Heights construction site, Land Department inspection photo 4, 12 November 2025

16 July 2025

6.7%+2.8 pts

  • 171 Garden Heights construction site, Land Department inspection photo 1, 16 July 2025
  • 171 Garden Heights construction site, Land Department inspection photo 2, 16 July 2025
  • 171 Garden Heights construction site, Land Department inspection photo 3, 16 July 2025
  • 171 Garden Heights construction site, Land Department inspection photo 4, 16 July 2025

2 April 2025

4.0%+4.0 pts

  • 171 Garden Heights construction site, Land Department inspection photo 1, 2 April 2025
  • 171 Garden Heights construction site, Land Department inspection photo 2, 2 April 2025
  • 171 Garden Heights construction site, Land Department inspection photo 3, 2 April 2025
  • 171 Garden Heights construction site, Land Department inspection photo 4, 2 April 2025

19 June 2024

0%

  • 171 Garden Heights construction site, Land Department inspection photo 1, 19 June 2024

All 34 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Jad Global Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in 171 Garden Heights?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will 171 Garden Heights be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around August 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of 171 Garden Heights is built?
34%, measured at the Land Department site inspection on 8 June 2026. The Land Department engineers have inspected the site 6 times since June 2024.
Is 171 Garden Heights delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building 171 Garden Heights?
The registered developer is Jad Global Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for 171 Garden Heights?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.