Evergrin House 2 construction progress
The registered completion date for Evergrin House 2 in Jumeirah Garden City is December 2026. At the last site inspection, in July 2026, it was 10% built. The developer is Obj1 Real Estate Development.
10%
Built, at the site inspection of 21 July 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- September 2033
- Construction started
- September 2025
- First registered
- October 2025
- Developer
- Obj1 Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 193
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ايفر جرين هاوس 2
- Project number
- 4114
- Site inspections
- 3
Schedule
Between September 2025 and July 2026 the site added about 1.0 points a month. At that rate it would finish around September 2033, more than three months after its registered date of December 2026.
Site inspections
21 July 2026
10%+6.4 pts
14 April 2026
3.9%+3.9 pts
25 September 2025
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Evergrin House 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Evergrin House 2 handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Evergrin House 2?
- Evergrin House 2 was 10% built at the site inspection on 21 July 2026. The site has been inspected 3 times since September 2025. The Land Department took 12 site photos at its inspections.
- Is Evergrin House 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Evergrin House 2?
- The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Evergrin House 2?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luminar Tower 1Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Evergrin HouseAlso by Obj1 Real Estate Development. 55%, Due June 2026, passed.
- Luminar Tower 2Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Vivid TowerAlso by Obj1 Real Estate Development. 12%, Due November 2026.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.