Skip to content

Evergrin House 2 construction progress

Evergrin House 2 in Jumeirah Garden City is 10% built at the Land Department inspection of July 2026. Developer Obj1 Real Estate Development. Completion registered for December 2026.

10%

Built, at the Land Department site inspection of 21 July 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
September 2033
Construction started
September 2025
Registered with the Land Department
October 2025
Units
193
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ايفر جرين هاوس 2
Land Department project number
4114
Land Department site inspections
3

Schedule

Between September 2025 and July 2026 the site added about 1.0 points a month. At that rate it would finish around September 2033, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

21 July 2026

10%+6.4 pts

  • Evergrin House 2 construction site, Land Department inspection photo 1, 21 July 2026
  • Evergrin House 2 construction site, Land Department inspection photo 2, 21 July 2026
  • Evergrin House 2 construction site, Land Department inspection photo 3, 21 July 2026
  • Evergrin House 2 construction site, Land Department inspection photo 4, 21 July 2026

14 April 2026

3.9%+3.9 pts

  • Evergrin House 2 construction site, Land Department inspection photo 1, 14 April 2026
  • Evergrin House 2 construction site, Land Department inspection photo 2, 14 April 2026
  • Evergrin House 2 construction site, Land Department inspection photo 3, 14 April 2026
  • Evergrin House 2 construction site, Land Department inspection photo 4, 14 April 2026

25 September 2025

0%

  • Evergrin House 2 construction site, Land Department inspection photo 1, 25 September 2025
  • Evergrin House 2 construction site, Land Department inspection photo 2, 25 September 2025

All 12 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Obj1 Real Estate Development has 14 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Evergrin House 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Evergrin House 2 be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around September 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Evergrin House 2 is built?
10%, measured at the Land Department site inspection on 21 July 2026. The Land Department engineers have inspected the site 3 times since September 2025.
Is Evergrin House 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Evergrin House 2?
The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Evergrin House 2?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.