Evergrin House 2 construction progress

The registered completion date for Evergrin House 2 in Jumeirah Garden City is December 2026. At the last site inspection, in July 2026, it was 10% built. The developer is Obj1 Real Estate Development.

10%

Built, at the site inspection of 21 July 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
September 2033
Construction started
September 2025
First registered
October 2025
Units
193
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ايفر جرين هاوس 2
Project number
4114
Site inspections
3

Schedule

Between September 2025 and July 2026 the site added about 1.0 points a month. At that rate it would finish around September 2033, more than three months after its registered date of December 2026.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 July 2026

10%+6.4 pts

  • Evergrin House 2 construction site, inspection photo 1, 21 July 2026
  • Evergrin House 2 construction site, inspection photo 2, 21 July 2026
  • Evergrin House 2 construction site, inspection photo 3, 21 July 2026
  • Evergrin House 2 construction site, inspection photo 4, 21 July 2026

14 April 2026

3.9%+3.9 pts

  • Evergrin House 2 construction site, inspection photo 1, 14 April 2026
  • Evergrin House 2 construction site, inspection photo 2, 14 April 2026
  • Evergrin House 2 construction site, inspection photo 3, 14 April 2026
  • Evergrin House 2 construction site, inspection photo 4, 14 April 2026

25 September 2025

0%

  • Evergrin House 2 construction site, inspection photo 1, 25 September 2025
  • Evergrin House 2 construction site, inspection photo 2, 25 September 2025

All 12 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Evergrin House 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Evergrin House 2 handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Evergrin House 2?
Evergrin House 2 was 10% built at the site inspection on 21 July 2026. The site has been inspected 3 times since September 2025. The Land Department took 12 site photos at its inspections.
Is Evergrin House 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Evergrin House 2?
The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Evergrin House 2?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.