Olivia Gardens Residence construction progress

The registered completion date for Olivia Gardens Residence in Jumeirah Garden City is April 2027. At the last site inspection, in November 2026, it was 24% built. The developer is Segrex Terra Development.

24%

Built, at the site inspection of 2 November 2026

Running behind its date

Registered completion date
April 2027
Finish at recent pace
January 2029
Construction started
April 2025
First registered
May 2025
Developer
Segrex Terra Development
Units
78
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
سكن حدائق أوليفا
Project number
3623
Site inspections
3

Schedule

Between April 2026 and November 2026 the site added about 2.8 points a month. At that rate it would finish around January 2029, more than three months after its registered date of April 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 November 2026

24%+19 pts

  • Olivia Gardens Residence construction site, inspection photo 1, 2 November 2026
  • Olivia Gardens Residence construction site, inspection photo 2, 2 November 2026
  • Olivia Gardens Residence construction site, inspection photo 3, 2 November 2026
  • Olivia Gardens Residence construction site, inspection photo 4, 2 November 2026

15 April 2026

5.5%+5.5 pts

  • Olivia Gardens Residence construction site, inspection photo 1, 15 April 2026
  • Olivia Gardens Residence construction site, inspection photo 2, 15 April 2026
  • Olivia Gardens Residence construction site, inspection photo 3, 15 April 2026
  • Olivia Gardens Residence construction site, inspection photo 4, 15 April 2026

24 March 2025

0%

  • Olivia Gardens Residence construction site, inspection photo 1, 24 March 2025
  • Olivia Gardens Residence construction site, inspection photo 2, 24 March 2025

All 18 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Own a unit in Olivia Gardens Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Olivia Gardens Residence handover date?
The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Olivia Gardens Residence?
Olivia Gardens Residence was 24% built at the site inspection on 2 November 2026. The site has been inspected 3 times since March 2025. The Land Department took 18 site photos at its inspections.
Is Olivia Gardens Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Olivia Gardens Residence?
The registered developer is Segrex Terra Development.
Which bank holds the escrow account for Olivia Gardens Residence?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.