Skip to content

Olivia Gardens Residence construction progress

Olivia Gardens Residence in Jumeirah Garden City is 5.5% built at the Land Department inspection of April 2026. Developer Segrex Terra Development. Completion registered for April 2027.

5.5%

Built, at the Land Department site inspection of 15 April 2026

Running behind its date

Completion date (Land Department)
April 2027
Finish at recent pace
August 2044
Construction started
April 2025
Registered with the Land Department
May 2025
Developer
Segrex Terra Development
Units
78
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
سكن حدائق أوليفا
Land Department project number
3623
Land Department site inspections
2

Schedule

Between March 2025 and April 2026 the site added about 0.4 points a month. At that rate it would finish around August 2044, more than three months after the April 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

15 April 2026

5.5%+5.5 pts

  • Olivia Gardens Residence construction site, Land Department inspection photo 1, 15 April 2026
  • Olivia Gardens Residence construction site, Land Department inspection photo 2, 15 April 2026
  • Olivia Gardens Residence construction site, Land Department inspection photo 3, 15 April 2026
  • Olivia Gardens Residence construction site, Land Department inspection photo 4, 15 April 2026

24 March 2025

0%

  • Olivia Gardens Residence construction site, Land Department inspection photo 1, 24 March 2025
  • Olivia Gardens Residence construction site, Land Department inspection photo 2, 24 March 2025

All 7 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Own a unit in Olivia Gardens Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Olivia Gardens Residence be completed?
The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around August 2044. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Olivia Gardens Residence is built?
5.5%, measured at the Land Department site inspection on 15 April 2026. The Land Department engineers have inspected the site 2 times since March 2025.
Is Olivia Gardens Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Olivia Gardens Residence?
The registered developer is Segrex Terra Development.
Which bank holds the escrow account for Olivia Gardens Residence?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.