Whitestone Residence construction progress

Whitestone Residence in Jumeirah Garden City is 3.0% built at the Land Department inspection of July 2026. Developer Axiom Prime Real Estate Development. Completion registered for October 2026.

3.0%

Built, at the Land Department site inspection of 6 July 2026

Running behind its date

Completion date (Land Department)
October 2026
Finish at recent pace
November 2067
Construction started
June 2025
Registered with the Land Department
June 2025
Developer
Axiom Prime Real Estate Development
Units
46
Escrow bank
Mashreq Bank
Name in Arabic
وايت ستون رزدنس
Land Department project number
3536
Land Department site inspections
2

Schedule

Between March 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around November 2067, more than three months after the October 2026 date registered with the Land Department.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 July 2026

3.0%+3.0 pts

  • Whitestone Residence construction site, Land Department inspection photo 1, 6 July 2026
  • Whitestone Residence construction site, Land Department inspection photo 2, 6 July 2026
  • Whitestone Residence construction site, Land Department inspection photo 3, 6 July 2026
  • Whitestone Residence construction site, Land Department inspection photo 4, 6 July 2026

19 March 2025

0%

  • Whitestone Residence construction site, Land Department inspection photo 1, 19 March 2025
  • Whitestone Residence construction site, Land Department inspection photo 2, 19 March 2025

All 6 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Own a unit in Whitestone Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Whitestone Residence be completed?
The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around November 2067. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Whitestone Residence is built?
3.0%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 2 times since March 2025.
Is Whitestone Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2026.
Who is building Whitestone Residence?
The registered developer is Axiom Prime Real Estate Development.
Which bank holds the escrow account for Whitestone Residence?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.