Whitestone Residence construction progress
Whitestone Residence in Jumeirah Garden City was registered to complete in October 2026 and is still under construction. At the last site inspection, in July 2026, it was 3.0% built. The developer is Axiom Prime Real Estate Development.
3.0%
Built, at the site inspection of 6 July 2026
1 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- November 2067
- Construction started
- June 2025
- First registered
- June 2025
- Developer
- Axiom Prime Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 47
- Escrow bank
- Mashreq Bank
- Name in Arabic
- وايت ستون رزدنس
- Project number
- 3536
- Site inspections
- 2
Schedule
Whitestone Residence was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around November 2067.
Site inspections
6 July 2026
3.0%+3.0 pts
19 March 2025
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Own a unit in Whitestone Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Whitestone Residence handover date?
- The registered completion date was October 2026, and the register still lists Whitestone Residence as under construction. At the pace of its recent inspections the site would reach 100% around November 2067. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Whitestone Residence?
- Whitestone Residence was 3.0% built at the site inspection on 6 July 2026. The site has been inspected 2 times since March 2025. The Land Department took 6 site photos at its inspections.
- Is Whitestone Residence delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building Whitestone Residence?
- The registered developer is Axiom Prime Real Estate Development.
- Which bank holds the escrow account for Whitestone Residence?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.