Brand Centro construction progress
Brand Centro in Jumeirah Garden City was registered to complete in July 2026 and is still under construction. At the last site inspection, in July 2026, it was 90% built. The developer is E M S Real Estate Development.
90%
Built, at the site inspection of 28 July 2026
4 months past its registered completion date
- Registered completion date
- July 2026
- Finish at recent pace
- September 2026
- Construction started
- October 2024
- First registered
- November 2024
- Developer
- E M S Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 56
- Escrow bank
- Emirates NBD
- Name in Arabic
- براند سنترو
- Project number
- 3235
- Site inspections
- 6
Schedule
Brand Centro was registered to complete in July 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 5.7 points a month. Kept at that rate, the site would reach 100% around September 2026.
Site inspections
28 July 2026
90%+22 pts
3 April 2026
68%+12 pts
3 February 2026
56%+14 pts
14 November 2025
42%+20 pts
30 June 2025
22%+22 pts
17 October 2024
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Own a unit in Brand Centro?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Brand Centro handover date?
- The registered completion date was July 2026, and the register still lists Brand Centro as under construction. At the pace of its recent inspections the site would reach 100% around September 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Brand Centro?
- Brand Centro was 90% built at the site inspection on 28 July 2026. The site has been inspected 6 times since October 2024. The Land Department took 43 site photos at its inspections.
- Is Brand Centro delayed?
- Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
- Who is building Brand Centro?
- The registered developer is E M S Real Estate Development.
- Which bank holds the escrow account for Brand Centro?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)