Cavara Central construction progress
Cavara Central in Jumeirah Garden City is 43% built at the site inspection of September 2026. Developer Cavara Real Estate Development. Completion registered for July 2026.
43%
Built, at the site inspection of 24 September 2026
3 months past its registered completion date
- Registered completion date
- July 2026
- Finish at recent pace
- April 2028
- Construction started
- January 2025
- First registered
- April 2025
- Developer
- Cavara Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 166
- Escrow bank
- Emirates NBD
- Name in Arabic
- كافارا سنترال
- Project number
- 3506
- Site inspections
- 6
Schedule
Cavara Central was registered to complete in July 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 3.0 points a month. Kept at that rate, the site would reach 100% around April 2028.
Site inspections
24 September 2026
43%+15 pts
8 June 2026
28%+11 pts
18 March 2026
17%+4.5 pts
19 November 2025
13%+11 pts
10 July 2025
2.1%+2.1 pts
15 January 2025
0%
Context
Jumeirah Garden City has 27 projects under construction, 31% built on average.
Cavara Real Estate Development has 3 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Cavara Central?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Cavara Central be completed?
- The registered completion date is July 2026. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to extend the date, so check the register before relying on it.
- How much of Cavara Central is built?
- 43%, measured at the site inspection on 24 September 2026. The site has been inspected 6 times since January 2025.
- Is Cavara Central delayed?
- Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
- Who is building Cavara Central?
- The registered developer is Cavara Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Cavara Central?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cavara 42Also by Cavara Real Estate Development. 76%, Due May 2026, passed.
- Cavara CircleAlso by Cavara Real Estate Development. 51%, Due August 2026, passed.
- The GrandalaNearby in Jumeirah Garden City. 86%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 31%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.













.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)