Cavara Central construction progress

Cavara Central in Jumeirah Garden City is 43% built at the site inspection of September 2026. Developer Cavara Real Estate Development. Completion registered for July 2026.

43%

Built, at the site inspection of 24 September 2026

3 months past its registered completion date

Registered completion date
July 2026
Finish at recent pace
April 2028
Construction started
January 2025
First registered
April 2025
Units
166
Escrow bank
Emirates NBD
Name in Arabic
كافارا سنترال
Project number
3506
Site inspections
6

Schedule

Cavara Central was registered to complete in July 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 3.0 points a month. Kept at that rate, the site would reach 100% around April 2028.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 September 2026

43%+15 pts

  • Cavara Central construction site, inspection photo 1, 24 September 2026
  • Cavara Central construction site, inspection photo 2, 24 September 2026
  • Cavara Central construction site, inspection photo 3, 24 September 2026
  • Cavara Central construction site, inspection photo 4, 24 September 2026

8 June 2026

28%+11 pts

  • Cavara Central construction site, inspection photo 1, 8 June 2026
  • Cavara Central construction site, inspection photo 2, 8 June 2026
  • Cavara Central construction site, inspection photo 3, 8 June 2026
  • Cavara Central construction site, inspection photo 4, 8 June 2026

18 March 2026

17%+4.5 pts

  • Cavara Central construction site, inspection photo 1, 18 March 2026
  • Cavara Central construction site, inspection photo 2, 18 March 2026
  • Cavara Central construction site, inspection photo 3, 18 March 2026
  • Cavara Central construction site, inspection photo 4, 18 March 2026

19 November 2025

13%+11 pts

  • Cavara Central construction site, inspection photo 1, 19 November 2025
  • Cavara Central construction site, inspection photo 2, 19 November 2025
  • Cavara Central construction site, inspection photo 3, 19 November 2025
  • Cavara Central construction site, inspection photo 4, 19 November 2025

10 July 2025

2.1%+2.1 pts

  • Cavara Central construction site, inspection photo 1, 10 July 2025
  • Cavara Central construction site, inspection photo 2, 10 July 2025
  • Cavara Central construction site, inspection photo 3, 10 July 2025
  • Cavara Central construction site, inspection photo 4, 10 July 2025

15 January 2025

0%

  • Cavara Central construction site, inspection photo 1, 15 January 2025
  • Cavara Central construction site, inspection photo 2, 15 January 2025

All 35 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 31% built on average.

Cavara Real Estate Development has 3 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Cavara Central?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Cavara Central be completed?
The registered completion date is July 2026. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to extend the date, so check the register before relying on it.
How much of Cavara Central is built?
43%, measured at the site inspection on 24 September 2026. The site has been inspected 6 times since January 2025.
Is Cavara Central delayed?
Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
Who is building Cavara Central?
The registered developer is Cavara Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Cavara Central?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.