Purvanchal Triana Residences construction progress

The registered completion date for Purvanchal Triana Residences in Jumeirah Garden City is March 2027. At the last site inspection, in November 2026, it was 36% built. The developer is Purvanchal Real Estate Developers.

36%

Built, at the site inspection of 20 November 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
February 2029
Construction started
August 2025
First registered
October 2025
Developer
Purvanchal Real Estate Developers
Units
72
Escrow bank
Bank of Baroda
Name in Arabic
بيورفانشهال تريانا ريزيدنسز
Project number
4095
Site inspections
5

Schedule

Between December 2025 and November 2026 the site added about 2.3 points a month. At that rate it would finish around February 2029, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 November 2026

36%+9.6 pts

  • Purvanchal Triana Residences construction site, inspection photo 1, 20 November 2026
  • Purvanchal Triana Residences construction site, inspection photo 2, 20 November 2026
  • Purvanchal Triana Residences construction site, inspection photo 3, 20 November 2026
  • Purvanchal Triana Residences construction site, inspection photo 4, 20 November 2026

3 August 2026

26%+11 pts

  • Purvanchal Triana Residences construction site, inspection photo 1, 3 August 2026
  • Purvanchal Triana Residences construction site, inspection photo 2, 3 August 2026
  • Purvanchal Triana Residences construction site, inspection photo 3, 3 August 2026
  • Purvanchal Triana Residences construction site, inspection photo 4, 3 August 2026

30 April 2026

15%+4.5 pts

  • Purvanchal Triana Residences construction site, inspection photo 1, 30 April 2026
  • Purvanchal Triana Residences construction site, inspection photo 2, 30 April 2026
  • Purvanchal Triana Residences construction site, inspection photo 3, 30 April 2026
  • Purvanchal Triana Residences construction site, inspection photo 4, 30 April 2026

30 December 2025

11%+11 pts

  • Purvanchal Triana Residences construction site, inspection photo 1, 30 December 2025
  • Purvanchal Triana Residences construction site, inspection photo 2, 30 December 2025
  • Purvanchal Triana Residences construction site, inspection photo 3, 30 December 2025
  • Purvanchal Triana Residences construction site, inspection photo 4, 30 December 2025

24 September 2025

0%

  • Purvanchal Triana Residences construction site, inspection photo 1, 24 September 2025
  • Purvanchal Triana Residences construction site, inspection photo 2, 24 September 2025

All 46 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Purvanchal Real Estate Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Purvanchal Triana Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Purvanchal Triana Residences handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Purvanchal Triana Residences?
Purvanchal Triana Residences was 36% built at the site inspection on 20 November 2026. The site has been inspected 5 times since September 2025. The Land Department took 46 site photos at its inspections.
Is Purvanchal Triana Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Purvanchal Triana Residences?
The registered developer is Purvanchal Real Estate Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Purvanchal Triana Residences?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.