Purvanchal Triana Residences construction progress

Purvanchal Triana Residences in Jumeirah Garden City is 26% built at the Land Department inspection of August 2026. Developer Purvanchal Real Estate Developers. Completion registered for March 2027.

26%

Built, at the Land Department site inspection of 3 August 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
December 2028
Construction started
August 2025
Registered with the Land Department
October 2025
Developer
Purvanchal Real Estate Developers
Units
72
Escrow bank
Bank of Baroda
Name in Arabic
بيورفانشهال تريانا ريزيدنسز
Land Department project number
4095
Land Department site inspections
4

Schedule

Between September 2025 and August 2026 the site added about 2.6 points a month. At that rate it would finish around December 2028, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 August 2026

26%+11 pts

  • Purvanchal Triana Residences construction site, Land Department inspection photo 1, 3 August 2026
  • Purvanchal Triana Residences construction site, Land Department inspection photo 2, 3 August 2026
  • Purvanchal Triana Residences construction site, Land Department inspection photo 3, 3 August 2026
  • Purvanchal Triana Residences construction site, Land Department inspection photo 4, 3 August 2026

30 April 2026

15%+4.5 pts

  • Purvanchal Triana Residences construction site, Land Department inspection photo 1, 30 April 2026
  • Purvanchal Triana Residences construction site, Land Department inspection photo 2, 30 April 2026
  • Purvanchal Triana Residences construction site, Land Department inspection photo 3, 30 April 2026
  • Purvanchal Triana Residences construction site, Land Department inspection photo 4, 30 April 2026

30 December 2025

11%+11 pts

  • Purvanchal Triana Residences construction site, Land Department inspection photo 1, 30 December 2025
  • Purvanchal Triana Residences construction site, Land Department inspection photo 2, 30 December 2025
  • Purvanchal Triana Residences construction site, Land Department inspection photo 3, 30 December 2025
  • Purvanchal Triana Residences construction site, Land Department inspection photo 4, 30 December 2025

24 September 2025

0%

  • Purvanchal Triana Residences construction site, Land Department inspection photo 1, 24 September 2025
  • Purvanchal Triana Residences construction site, Land Department inspection photo 2, 24 September 2025

All 38 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Purvanchal Real Estate Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Purvanchal Triana Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Purvanchal Triana Residences be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around December 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Purvanchal Triana Residences is built?
26%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 4 times since September 2025.
Is Purvanchal Triana Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Purvanchal Triana Residences?
The registered developer is Purvanchal Real Estate Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Purvanchal Triana Residences?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.