Stamn Yuni construction progress
The registered completion date for Stamn Yuni in Jumeirah Garden City is March 2027. At the last site inspection, in November 2026, it was 21% built. The developer is Stamn Real Estate Development.
21%
Built, at the site inspection of 20 November 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- July 2029
- Construction started
- July 2025
- First registered
- April 2025
- Developer
- Stamn Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 88
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ستيمن يوني
- Project number
- 3596
- Site inspections
- 4
Schedule
Between March 2026 and November 2026 the site added about 2.5 points a month. At that rate it would finish around July 2029, more than three months after its registered date of March 2027.
Site inspections
20 November 2026
21%+9.5 pts
31 July 2026
12%+9.4 pts
31 March 2026
2.1%+2.1 pts
24 March 2025
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Stamn Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Stamn Yuni?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Stamn Yuni handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Stamn Yuni?
- Stamn Yuni was 21% built at the site inspection on 20 November 2026. The site has been inspected 4 times since March 2025. The Land Department took 19 site photos at its inspections.
- Is Stamn Yuni delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Stamn Yuni?
- The registered developer is Stamn Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Stamn Yuni?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Stamn OneAlso by Stamn Real Estate Development. 42%, Due October 2026, passed.
- Nautis ResidencesAlso by Stamn Real Estate Development. 0.9%, Due August 2027.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)