Stamn Yuni construction progress

The registered completion date for Stamn Yuni in Jumeirah Garden City is March 2027. At the last site inspection, in November 2026, it was 21% built. The developer is Stamn Real Estate Development.

21%

Built, at the site inspection of 20 November 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
July 2029
Construction started
July 2025
First registered
April 2025
Units
88
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ستيمن يوني
Project number
3596
Site inspections
4

Schedule

Between March 2026 and November 2026 the site added about 2.5 points a month. At that rate it would finish around July 2029, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 November 2026

21%+9.5 pts

  • Stamn Yuni construction site, inspection photo 1, 20 November 2026
  • Stamn Yuni construction site, inspection photo 2, 20 November 2026
  • Stamn Yuni construction site, inspection photo 3, 20 November 2026
  • Stamn Yuni construction site, inspection photo 4, 20 November 2026

31 July 2026

12%+9.4 pts

  • Stamn Yuni construction site, inspection photo 1, 31 July 2026
  • Stamn Yuni construction site, inspection photo 2, 31 July 2026
  • Stamn Yuni construction site, inspection photo 3, 31 July 2026
  • Stamn Yuni construction site, inspection photo 4, 31 July 2026

31 March 2026

2.1%+2.1 pts

  • Stamn Yuni construction site, inspection photo 1, 31 March 2026
  • Stamn Yuni construction site, inspection photo 2, 31 March 2026
  • Stamn Yuni construction site, inspection photo 3, 31 March 2026

24 March 2025

0%

  • Stamn Yuni construction site, inspection photo 1, 24 March 2025
  • Stamn Yuni construction site, inspection photo 2, 24 March 2025

All 19 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Stamn Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Stamn Yuni?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Stamn Yuni handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Stamn Yuni?
Stamn Yuni was 21% built at the site inspection on 20 November 2026. The site has been inspected 4 times since March 2025. The Land Department took 19 site photos at its inspections.
Is Stamn Yuni delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Stamn Yuni?
The registered developer is Stamn Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Stamn Yuni?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.