Stamn Yuni construction progress

Stamn Yuni in Jumeirah Garden City is 12% built at the Land Department inspection of July 2026. Developer Stamn Real Estate Development. Completion registered for March 2027.

12%

Built, at the Land Department site inspection of 31 July 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
September 2029
Construction started
July 2025
Registered with the Land Department
April 2025
Units
88
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ستيمن يوني
Land Department project number
3596
Land Department site inspections
3

Schedule

Between March 2026 and July 2026 the site added about 2.4 points a month. At that rate it would finish around September 2029, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 July 2026

12%+9.4 pts

  • Stamn Yuni construction site, Land Department inspection photo 1, 31 July 2026
  • Stamn Yuni construction site, Land Department inspection photo 2, 31 July 2026
  • Stamn Yuni construction site, Land Department inspection photo 3, 31 July 2026
  • Stamn Yuni construction site, Land Department inspection photo 4, 31 July 2026

31 March 2026

2.1%+2.1 pts

  • Stamn Yuni construction site, Land Department inspection photo 1, 31 March 2026
  • Stamn Yuni construction site, Land Department inspection photo 2, 31 March 2026
  • Stamn Yuni construction site, Land Department inspection photo 3, 31 March 2026

24 March 2025

0%

  • Stamn Yuni construction site, Land Department inspection photo 1, 24 March 2025
  • Stamn Yuni construction site, Land Department inspection photo 2, 24 March 2025

All 11 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Stamn Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Stamn Yuni?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Stamn Yuni be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around September 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Stamn Yuni is built?
12%, measured at the Land Department site inspection on 31 July 2026. The Land Department engineers have inspected the site 3 times since March 2025.
Is Stamn Yuni delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Stamn Yuni?
The registered developer is Stamn Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Stamn Yuni?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.