Off-plan projects in Arjan
23 projects in Arjan are under construction. On average they are 48% built. 8 have passed their registered completion date. The next one due is One Beverly, in December 2026.
- Samana Mykonos SignatureSamana International Real Estate Development86%Due April 2026, passed
- Aryene GreensDiamond Star Real Estate Development80%Due November 2022, passed
- Cavara 42Cavara Real Estate Development76%Due May 2026, passed
- Ashley HillsTownx Real Estate Development74%Due March 2027
- One BeverlyH M B Homes Real Estate Development73%Due December 2026
- Samana SkyrosSamana Signature Real Estate Developments71%Due April 2026, passed
- Elano By Oro24Oro24 Real Estate Development70%Due October 2025, passed
- Gardens 2Iman Developers68%Due December 2025, passed
- Marquis InsigniaMarquis Star Development67%No date set
- Vincitore VolareVincitore Premium Real Estate Development63%Due June 2025, passed
- Parkside BoulevardTabeer Real Estate Development60%Due December 2027
- Binghatti HillcrestBinghatti Developers60%Due December 2026
- Empire EstatesEmpire Real Estate Developments60%Due December 2026
- Floarea GrandeMashriq Elite Real Estate Development48%Due August 2027
- Vincitore Dolce VitaVincitore Premium Real Estate Development40%No date set
- Trinity By KarmaKarma Realty Developers31%Due December 2026
- Bond EnclavePearlshire Real Estate Development20%Due November 2027
- Kyoto By Oro24Oro24 Real Estate Development17%Due September 2026, passed
- The Central DowntownAqua Properties10%Due March 2028
- ButterflyDesert Falcon Real Estate Development8.2%Due January 2029
- The LxMulk Properties4.9%Due August 2027
- Samana Imperial GardenSamana Signature Real Estate Developments4.2%Due December 2028
- Marquis OneMarquis Home Developer0.3%Due December 2028
Questions
How many off-plan projects are under construction in Arjan?
23 projects are under construction in Arjan, 48% built on average at the latest site inspections.
Which Arjan projects are due to finish next?
By registered completion date: One Beverly (December 2026, 73% built), Trinity By Karma (December 2026, 31% built) and Binghatti Hillcrest (December 2026, 60% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
How many Arjan projects are past their completion date?
8 of 23, among them Aryene Greens, Vincitore Volare and Elano By Oro24. A project counts as late once its registered completion date has passed before it reaches 100%.
Which developers are building in Arjan?
The developers with the most projects here are Oro24 Real Estate Development (2), Samana Signature Real Estate Developments (2) and Vincitore Premium Real Estate Development (2), out of 20 building in Arjan.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.