Off-plan projects in Arjan
23 projects in Arjan are under construction according to the Dubai Land Department. On average they are 46% built. 7 have passed their registered completion date. The next one due is Trinity By Karma, in December 2026.
- Samana Mykonos SignatureSamana International Real Estate Development80%Due April 2026, passed
- Aryene GreensDiamond Star Real Estate Development80%Due November 2022, passed
- Rose Gardens 3Cavara Real Estate Development76%Due May 2026, passed
- Ashley HillsTownx Real Estate Development74%Due March 2027
- One BeverlyH M B Homes Real Estate Development73%No date set
- Samana SkyrosSamana Signature Real Estate Developments71%Due April 2026, passed
- Elano By Oro24Oro24 Real Estate Development70%Due October 2025, passed
- Gardens 2Iman Developers68%Due December 2025, passed
- Vincitore VolareVincitore Premium Real Estate Development63%Due June 2025, passed
- Binghatti HillcrestBinghatti Developers60%Due December 2026
- Empire EstatesEmpire Real Estate Developments60%Due December 2026
- Marquis InsigniaMarquis Star Development56%No date set
- Parkside BoulevardTabeer Real Estate Development52%Due December 2027
- Floarea GrandeMashriq Elite Real Estate Development48%Due August 2027
- Trinity By KarmaKarma Realty Developers31%Due December 2026
- Vincitore Dolce VitaVincitore Premium Real Estate Development22%No date set
- Bond EnclavePearlshire Real Estate Development20%No date set
- Kyoto By Oro24Oro24 Real Estate Development17%No date set
- The Central DowntownAqua Properties10%Due March 2028
- ButterflyDesert Falcon Real Estate Development7.7%Due January 2029
- The LxMulk Properties4.9%Due August 2027
- Samana Imperial GardenSamana Signature Real Estate Developments3.8%Due December 2028
- Marquis OneMarquis Home Developer0%Due December 2028
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its full inspection history, recent site photos and whether it is keeping pace with that date.
Buying or already own off-plan? What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.