Gardens 2 construction progress
Gardens 2 in Arjan was registered to complete in December 2025 and is still under construction. At the last site inspection, in December 2025, it was 68% built. The developer is Iman Developers.
68%
Built, at the site inspection of 16 December 2025
11 months past its registered completion date
- Registered completion date
- December 2025
- Finish at recent pace
- June 2026
- Construction started
- April 2024
- First registered
- May 2024
- Developer
- Iman Developers
- Community
- Arjan
- Units
- 223
- Escrow bank
- Emirates NBD
- Name in Arabic
- غاردنز 2
- Project number
- 2938
- Site inspections
- 4
Schedule
Gardens 2 was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 5.4 points a month. Kept at that rate, the site would reach 100% around June 2026.
Site inspections
16 December 2025
68%+28 pts
1 August 2025
40%+18 pts
2 April 2025
23%+23 pts
26 January 2024
0%
Context
Arjan has 23 projects under construction, 48% built on average.
Iman Developers has 10 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Gardens 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Gardens 2 handover date?
- The registered completion date was December 2025, and the register still lists Gardens 2 as under construction. At the pace of its recent inspections the site would reach 100% around June 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Gardens 2?
- Gardens 2 was 68% built at the site inspection on 16 December 2025. The site has been inspected 4 times since January 2024. The Land Department took 30 site photos at its inspections.
- Is Gardens 2 delayed?
- Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
- Who is building Gardens 2?
- The registered developer is Iman Developers. It has 9 other projects under construction in Dubai.
- Which bank holds the escrow account for Gardens 2?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 10 Oxford By ImanAlso by Iman Developers. 91%.
- One Park Central By ImanAlso by Iman Developers. 32%, Due June 2027.
- One Sky Park By ImanAlso by Iman Developers. 22%, Due March 2028.
- One Park Square By ImanAlso by Iman Developers. 20%, Due June 2028.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)