Gardens 2 construction progress

Gardens 2 in Arjan is 68% built at the Land Department inspection of December 2025. Developer Iman Developers. Completion registered for December 2025.

68%

Built, at the Land Department site inspection of 16 December 2025

9 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
June 2026
Construction started
April 2024
Registered with the Land Department
May 2024
Community
Arjan
Units
223
Escrow bank
Emirates NBD
Name in Arabic
غاردنز 2
Land Department project number
2938
Land Department site inspections
4

Schedule

Gardens 2 was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 5.4 points a month. Kept at that rate, the site would reach 100% around June 2026.

0%25%50%75%100%2025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 December 2025

68%+28 pts

  • Gardens 2 construction site, Land Department inspection photo 1, 16 December 2025
  • Gardens 2 construction site, Land Department inspection photo 2, 16 December 2025
  • Gardens 2 construction site, Land Department inspection photo 3, 16 December 2025
  • Gardens 2 construction site, Land Department inspection photo 4, 16 December 2025

1 August 2025

40%+18 pts

  • Gardens 2 construction site, Land Department inspection photo 1, 1 August 2025
  • Gardens 2 construction site, Land Department inspection photo 2, 1 August 2025
  • Gardens 2 construction site, Land Department inspection photo 3, 1 August 2025
  • Gardens 2 construction site, Land Department inspection photo 4, 1 August 2025

2 April 2025

23%+23 pts

  • Gardens 2 construction site, Land Department inspection photo 1, 2 April 2025
  • Gardens 2 construction site, Land Department inspection photo 2, 2 April 2025
  • Gardens 2 construction site, Land Department inspection photo 3, 2 April 2025
  • Gardens 2 construction site, Land Department inspection photo 4, 2 April 2025

26 January 2024

0%

  • Gardens 2 construction site, Land Department inspection photo 1, 26 January 2024
  • Gardens 2 construction site, Land Department inspection photo 2, 26 January 2024

All 30 site photos, by inspection date

Context

Arjan has 23 projects under construction, 46% built on average.

Iman Developers has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Gardens 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Gardens 2 be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around June 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Gardens 2 is built?
68%, measured at the Land Department site inspection on 16 December 2025. The Land Department engineers have inspected the site 4 times since January 2024.
Is Gardens 2 delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Gardens 2?
The registered developer is Iman Developers. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Gardens 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.