Gardens 2 construction progress
Gardens 2 in Arjan is 68% built at the Land Department inspection of December 2025. Developer Iman Developers. Completion registered for December 2025.
68%
Built, at the Land Department site inspection of 16 December 2025
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- June 2026
- Construction started
- April 2024
- Registered with the Land Department
- May 2024
- Developer
- Iman Developers
- Community
- Arjan
- Units
- 223
- Escrow bank
- Emirates NBD
- Name in Arabic
- غاردنز 2
- Land Department project number
- 2938
- Land Department site inspections
- 4
Schedule
Gardens 2 was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 5.4 points a month. Kept at that rate, the site would reach 100% around June 2026.
Site inspections
16 December 2025
68%+28 pts
1 August 2025
40%+18 pts
2 April 2025
23%+23 pts
26 January 2024
0%
Context
Arjan has 23 projects under construction, 46% built on average.
Iman Developers has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Gardens 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Gardens 2 be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around June 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Gardens 2 is built?
- 68%, measured at the Land Department site inspection on 16 December 2025. The Land Department engineers have inspected the site 4 times since January 2024.
- Is Gardens 2 delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Gardens 2?
- The registered developer is Iman Developers. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Gardens 2?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 10 Oxford By ImanAlso by Iman Developers. 91%.
- One Park Central By ImanAlso by Iman Developers. 20%, Due June 2027.
- One Sky Park By ImanAlso by Iman Developers. 9.0%, Due March 2028.
- One Park Square By ImanAlso by Iman Developers. 20%.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 80%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)