Vincitore Dolce Vita construction progress

Vincitore Dolce Vita in Arjan is 22% built at the Land Department inspection of April 2026. Developer Vincitore Premium Real Estate Development.

22%

Built, at the Land Department site inspection of 22 April 2026

Finish at recent pace
March 2030
Construction started
June 2023
Registered with the Land Department
September 2023
Community
Arjan
Units
715
Escrow bank
Mashreq Bank
Name in Arabic
فينسيتور دولشي فيتا
Land Department project number
2669
Land Department site inspections
6

Schedule

Since July 2025 Vincitore Dolce Vita has added about 1.7 points a month. At that rate the site reaches 100% around March 2030. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

22 April 2026

22%+5.4 pts

  • Vincitore Dolce Vita construction site, Land Department inspection photo 1, 22 April 2026
  • Vincitore Dolce Vita construction site, Land Department inspection photo 2, 22 April 2026
  • Vincitore Dolce Vita construction site, Land Department inspection photo 3, 22 April 2026
  • Vincitore Dolce Vita construction site, Land Department inspection photo 4, 22 April 2026

12 December 2025

17%+9.6 pts

  • Vincitore Dolce Vita construction site, Land Department inspection photo 1, 12 December 2025
  • Vincitore Dolce Vita construction site, Land Department inspection photo 2, 12 December 2025
  • Vincitore Dolce Vita construction site, Land Department inspection photo 3, 12 December 2025
  • Vincitore Dolce Vita construction site, Land Department inspection photo 4, 12 December 2025

21 July 2025

7.1%+1.2 pts

  • Vincitore Dolce Vita construction site, Land Department inspection photo 1, 21 July 2025
  • Vincitore Dolce Vita construction site, Land Department inspection photo 2, 21 July 2025
  • Vincitore Dolce Vita construction site, Land Department inspection photo 3, 21 July 2025
  • Vincitore Dolce Vita construction site, Land Department inspection photo 4, 21 July 2025

16 December 2024

5.8%+5.8 pts

  • Vincitore Dolce Vita construction site, Land Department inspection photo 1, 16 December 2024
  • Vincitore Dolce Vita construction site, Land Department inspection photo 2, 16 December 2024
  • Vincitore Dolce Vita construction site, Land Department inspection photo 3, 16 December 2024
  • Vincitore Dolce Vita construction site, Land Department inspection photo 4, 16 December 2024

26 June 2024

0%+0.0 pts

  • Vincitore Dolce Vita construction site, Land Department inspection photo 1, 26 June 2024
  • Vincitore Dolce Vita construction site, Land Department inspection photo 2, 26 June 2024

12 June 2023

0%

  • Vincitore Dolce Vita construction site, Land Department inspection photo 1, 12 June 2023
  • Vincitore Dolce Vita construction site, Land Department inspection photo 2, 12 June 2023

All 28 site photos, by inspection date

Context

Arjan has 23 projects under construction, 46% built on average.

Vincitore Premium Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Vincitore Dolce Vita?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vincitore Dolce Vita be completed?
The Land Department has no completion date on record for Vincitore Dolce Vita yet.
How much of Vincitore Dolce Vita is built?
22%, measured at the Land Department site inspection on 22 April 2026. The Land Department engineers have inspected the site 6 times since June 2023.
Who is building Vincitore Dolce Vita?
The registered developer is Vincitore Premium Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Vincitore Dolce Vita?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.