Skip to content

Bond Enclave construction progress

The registered completion date for Bond Enclave in Arjan is November 2027. At the last site inspection, in July 2026, it was 20% built. The developer is Pearlshire Real Estate Development.

20%

Built, at the site inspection of 20 July 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
May 2030
Construction started
June 2025
First registered
January 2025
Developer
Pearlshire Real Estate Development
Community
Arjan
Units
158
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بوند انكلاف
Project number
3421
Site inspections
3

Schedule

Between September 2025 and July 2026 the site added about 1.8 points a month. At that rate it would finish around May 2030, more than three months after its registered date of November 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 July 2026

20%+17 pts

  • Bond Enclave construction site, inspection photo 1, 20 July 2026
  • Bond Enclave construction site, inspection photo 2, 20 July 2026
  • Bond Enclave construction site, inspection photo 3, 20 July 2026
  • Bond Enclave construction site, inspection photo 4, 20 July 2026

25 September 2025

2.9%+2.9 pts

  • Bond Enclave construction site, inspection photo 1, 25 September 2025
  • Bond Enclave construction site, inspection photo 2, 25 September 2025
  • Bond Enclave construction site, inspection photo 3, 25 September 2025
  • Bond Enclave construction site, inspection photo 4, 25 September 2025

6 December 2024

0%

  • Bond Enclave construction site, inspection photo 1, 6 December 2024
  • Bond Enclave construction site, inspection photo 2, 6 December 2024

All 12 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Own a unit in Bond Enclave?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Bond Enclave handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Bond Enclave?
Bond Enclave was 20% built at the site inspection on 20 July 2026. The site has been inspected 3 times since December 2024. The Land Department took 12 site photos at its inspections.
Is Bond Enclave delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Bond Enclave?
The registered developer is Pearlshire Real Estate Development.
Which bank holds the escrow account for Bond Enclave?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.