Bond Enclave construction progress
The registered completion date for Bond Enclave in Arjan is November 2027. At the last site inspection, in July 2026, it was 20% built. The developer is Pearlshire Real Estate Development.
20%
Built, at the site inspection of 20 July 2026
Running behind its date
- Registered completion date
- November 2027
- Finish at recent pace
- May 2030
- Construction started
- June 2025
- First registered
- January 2025
- Developer
- Pearlshire Real Estate Development
- Community
- Arjan
- Units
- 158
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- بوند انكلاف
- Project number
- 3421
- Site inspections
- 3
Schedule
Between September 2025 and July 2026 the site added about 1.8 points a month. At that rate it would finish around May 2030, more than three months after its registered date of November 2027.
Site inspections
20 July 2026
20%+17 pts
25 September 2025
2.9%+2.9 pts
6 December 2024
0%
Context
Arjan has 23 projects under construction, 48% built on average.
Own a unit in Bond Enclave?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Bond Enclave handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Bond Enclave?
- Bond Enclave was 20% built at the site inspection on 20 July 2026. The site has been inspected 3 times since December 2024. The Land Department took 12 site photos at its inspections.
- Is Bond Enclave delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Bond Enclave?
- The registered developer is Pearlshire Real Estate Development.
- Which bank holds the escrow account for Bond Enclave?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.