Ashley Hills construction progress
The registered completion date for Ashley Hills in Arjan is March 2027. At the last site inspection, in June 2026, it was 74% built. The developer is Townx Real Estate Development.
74%
Built, at the site inspection of 10 June 2026
On pace for its date
- Registered completion date
- March 2027
- Finish at recent pace
- October 2026
- Construction started
- February 2025
- First registered
- September 2025
- Developer
- Townx Real Estate Development
- Community
- Arjan
- Units
- 616
- Escrow bank
- Mashreq Bank
- Name in Arabic
- اشلي هيلز
- Project number
- 3723
- Site inspections
- 4
Schedule
Since August 2025 Ashley Hills has added about 5.6 points a month. That puts 100% around October 2026, within three months of its registered completion date of March 2027.
Site inspections
10 June 2026
74%+22 pts
19 February 2026
52%+13 pts
19 November 2025
39%+19 pts
18 August 2025
20%
Context
Arjan has 23 projects under construction, 48% built on average.
Townx Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Ashley Hills?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ashley Hills handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ashley Hills?
- Ashley Hills was 74% built at the site inspection on 10 June 2026. The site has been inspected 4 times since August 2025. The Land Department took 32 site photos at its inspections.
- Is Ashley Hills delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
- Who is building Ashley Hills?
- The registered developer is Townx Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Ashley Hills?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 11 Hills ParkAlso by Townx Real Estate Development. 80%, Due March 2027.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)







.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)