Samana Imperial Garden construction progress
Samana Imperial Garden in Arjan is 3.8% built at the Land Department inspection of June 2026. Developer Samana Signature Real Estate Developments. Completion registered for December 2028.
3.8%
Built, at the Land Department site inspection of 19 June 2026
Running behind its date
- Completion date (Land Department)
- December 2028
- Finish at recent pace
- June 2040
- Construction started
- July 2025
- Registered with the Land Department
- September 2025
- Community
- Arjan
- Units
- 344
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- سامانا امبريال جاردن
- Land Department project number
- 3797
- Land Department site inspections
- 4
Schedule
Between December 2025 and June 2026 the site added about 0.6 points a month. At that rate it would finish around June 2040, more than three months after the December 2028 date registered with the Land Department.
Site inspections
19 June 2026
3.8%+1.4 pts
30 April 2026
2.3%+2.1 pts
16 December 2025
0.3%+0.3 pts
1 June 2025
0%
Context
Arjan has 23 projects under construction, 46% built on average.
Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Samana Imperial Garden?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Samana Imperial Garden be completed?
- The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around June 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Samana Imperial Garden is built?
- 3.8%, measured at the Land Department site inspection on 19 June 2026. The Land Department engineers have inspected the site 4 times since June 2025.
- Is Samana Imperial Garden delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Samana Imperial Garden?
- The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Imperial Garden?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana SkyrosAlso by Samana Signature Real Estate Developments. 71%, Due April 2026, passed.
- Samana Lake ViewsAlso by Samana Signature Real Estate Developments. 23%.
- Samana Lake Views 2Also by Samana Signature Real Estate Developments. 8.9%.
- Samana Barari LagoonsAlso by Samana Signature Real Estate Developments. 12%.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 80%, Due April 2026, passed.
- Elano By Oro24Nearby in Arjan. 70%, Due October 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.



.jpeg&w=3840&q=75)