Samana Imperial Garden construction progress

The registered completion date for Samana Imperial Garden in Arjan is December 2028. At the last site inspection, in October 2026, it was 4.2% built. The developer is Samana Signature Real Estate Developments.

4.2%

Built, at the site inspection of 23 October 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
June 2047
Construction started
July 2025
First registered
September 2025
Community
Arjan
Units
344
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سامانا امبريال جاردن
Project number
3797
Site inspections
5

Schedule

Between December 2025 and October 2026 the site added about 0.4 points a month. At that rate it would finish around June 2047, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 October 2026

4.2%+0.5 pts

  • Samana Imperial Garden construction site, inspection photo 1, 23 October 2026
  • Samana Imperial Garden construction site, inspection photo 2, 23 October 2026
  • Samana Imperial Garden construction site, inspection photo 3, 23 October 2026

19 June 2026

3.8%+1.4 pts

  • Samana Imperial Garden construction site, inspection photo 1, 19 June 2026
  • Samana Imperial Garden construction site, inspection photo 2, 19 June 2026

30 April 2026

2.3%+2.1 pts

  • Samana Imperial Garden construction site, inspection photo 1, 30 April 2026
  • Samana Imperial Garden construction site, inspection photo 2, 30 April 2026
  • Samana Imperial Garden construction site, inspection photo 3, 30 April 2026

16 December 2025

0.3%+0.3 pts

  • Samana Imperial Garden construction site, inspection photo 1, 16 December 2025
  • Samana Imperial Garden construction site, inspection photo 2, 16 December 2025
  • Samana Imperial Garden construction site, inspection photo 3, 16 December 2025
  • Samana Imperial Garden construction site, inspection photo 4, 16 December 2025

1 June 2025

0%

  • Samana Imperial Garden construction site, inspection photo 1, 1 June 2025
  • Samana Imperial Garden construction site, inspection photo 2, 1 June 2025

All 14 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Samana Imperial Garden?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Imperial Garden handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2047. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Imperial Garden?
Samana Imperial Garden was 4.2% built at the site inspection on 23 October 2026. The site has been inspected 5 times since June 2025. The Land Department took 14 site photos at its inspections.
Is Samana Imperial Garden delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Samana Imperial Garden?
The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Imperial Garden?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.