Samana Imperial Garden construction progress
The registered completion date for Samana Imperial Garden in Arjan is December 2028. At the last site inspection, in October 2026, it was 4.2% built. The developer is Samana Signature Real Estate Developments.
4.2%
Built, at the site inspection of 23 October 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- June 2047
- Construction started
- July 2025
- First registered
- September 2025
- Community
- Arjan
- Units
- 344
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- سامانا امبريال جاردن
- Project number
- 3797
- Site inspections
- 5
Schedule
Between December 2025 and October 2026 the site added about 0.4 points a month. At that rate it would finish around June 2047, more than three months after its registered date of December 2028.
Site inspections
23 October 2026
4.2%+0.5 pts
19 June 2026
3.8%+1.4 pts
30 April 2026
2.3%+2.1 pts
16 December 2025
0.3%+0.3 pts
1 June 2025
0%
Context
Arjan has 23 projects under construction, 48% built on average.
Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Samana Imperial Garden?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Imperial Garden handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2047. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samana Imperial Garden?
- Samana Imperial Garden was 4.2% built at the site inspection on 23 October 2026. The site has been inspected 5 times since June 2025. The Land Department took 14 site photos at its inspections.
- Is Samana Imperial Garden delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Samana Imperial Garden?
- The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Imperial Garden?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana SkyrosAlso by Samana Signature Real Estate Developments. 71%, Due April 2026, passed.
- Samana Lake ViewsAlso by Samana Signature Real Estate Developments. 23%.
- Samana Lake Views 2Also by Samana Signature Real Estate Developments. 12%.
- Samana Barari LagoonsAlso by Samana Signature Real Estate Developments. 17%, Due March 2028.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Elano By Oro24Nearby in Arjan. 70%, Due October 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)