Kyoto By Oro24 construction progress
Kyoto By Oro24 in Arjan was registered to complete in September 2026 and is still under construction. At the last site inspection, in September 2026, it was 17% built. The developer is Oro24 Real Estate Development.
17%
Built, at the site inspection of 11 September 2026
2 months past its registered completion date
- Registered completion date
- September 2026
- Finish at recent pace
- June 2031
- Construction started
- June 2023
- First registered
- June 2023
- Developer
- Oro24 Real Estate Development
- Community
- Arjan
- Units
- 708
- Escrow bank
- Zand Bank
- Name in Arabic
- كيوتو من أورو 24
- Project number
- 2702
- Site inspections
- 6
Schedule
Kyoto By Oro24 was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 1.5 points a month. Kept at that rate, the site would reach 100% around June 2031.
Site inspections
11 September 2026
17%+9.3 pts
2 March 2026
7.7%+2.3 pts
24 July 2025
5.4%+2.5 pts
11 February 2025
2.9%+2.8 pts
31 October 2023
0%+0.0 pts
23 June 2023
0%
Context
Arjan has 23 projects under construction, 48% built on average.
Oro24 Real Estate Development has 4 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Kyoto By Oro24?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Kyoto By Oro24 handover date?
- The registered completion date was September 2026, and the register still lists Kyoto By Oro24 as under construction. At the pace of its recent inspections the site would reach 100% around June 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Kyoto By Oro24?
- Kyoto By Oro24 was 17% built at the site inspection on 11 September 2026. The site has been inspected 6 times since June 2023. The Land Department took 22 site photos at its inspections.
- Is Kyoto By Oro24 delayed?
- Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
- Who is building Kyoto By Oro24?
- The registered developer is Oro24 Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Kyoto By Oro24?
- Zand Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Levanto By Oro24Also by Oro24 Real Estate Development. 66%, Due December 2025, passed.
- Elano By Oro24Also by Oro24 Real Estate Development. 70%, Due October 2025, passed.
- Albero By Oro24Also by Oro24 Real Estate Development. 45%.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






-Enablaing%2520work%2520(10).jpg&w=3840&q=75)
-Enablaing%2520work%2520(1).jpg&w=3840&q=75)
-Dewatering%2520(3).jpg&w=3840&q=75)
-Enablaing%2520work%2520(4).jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)