Trinity By Karma construction progress
The registered completion date for Trinity By Karma in Arjan is December 2026. At the last site inspection, in September 2026, it was 31% built. The developer is Karma Realty Developers.
31%
Built, at the site inspection of 30 September 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- August 2030
- Construction started
- July 2024
- First registered
- March 2024
- Developer
- Karma Realty Developers
- Community
- Arjan
- Units
- 309
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ترينيتي بواسطة كارما
- Project number
- 2933
- Site inspections
- 7
Schedule
Between January 2026 and September 2026 the site added about 1.5 points a month. At that rate it would finish around August 2030, more than three months after its registered date of December 2026.
Site inspections
30 September 2026
31%+8.6 pts
6 May 2026
22%+4.3 pts
6 January 2026
18%+4.2 pts
2 September 2025
14%+12 pts
13 March 2025
1.6%+1.6 pts
12 November 2024
0%
22 January 2024
0%
Context
Arjan has 23 projects under construction, 48% built on average.
Karma Realty Developers has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Trinity By Karma?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Trinity By Karma handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Trinity By Karma?
- Trinity By Karma was 31% built at the site inspection on 30 September 2026. The site has been inspected 7 times since January 2024. The Land Department took 44 site photos at its inspections.
- Is Trinity By Karma delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Trinity By Karma?
- The registered developer is Karma Realty Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Trinity By Karma?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Milos By KarmaAlso by Karma Realty Developers. 0.4%, Due April 2027.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)