The registered completion date for Trinity By Karma in Arjan is December 2026. At the last site inspection, in September 2026, it was 31% built. The developer is Karma Realty Developers.

31%

Built, at the site inspection of 30 September 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
August 2030
Construction started
July 2024
First registered
March 2024
Developer
Karma Realty Developers
Community
Arjan
Units
309
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ترينيتي بواسطة كارما
Project number
2933
Site inspections
7

Schedule

Between January 2026 and September 2026 the site added about 1.5 points a month. At that rate it would finish around August 2030, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2026

31%+8.6 pts

  • Trinity By Karma construction site, inspection photo 1, 30 September 2026
  • Trinity By Karma construction site, inspection photo 2, 30 September 2026
  • Trinity By Karma construction site, inspection photo 3, 30 September 2026
  • Trinity By Karma construction site, inspection photo 4, 30 September 2026

6 May 2026

22%+4.3 pts

  • Trinity By Karma construction site, inspection photo 1, 6 May 2026
  • Trinity By Karma construction site, inspection photo 2, 6 May 2026
  • Trinity By Karma construction site, inspection photo 3, 6 May 2026
  • Trinity By Karma construction site, inspection photo 4, 6 May 2026

6 January 2026

18%+4.2 pts

  • Trinity By Karma construction site, inspection photo 1, 6 January 2026
  • Trinity By Karma construction site, inspection photo 2, 6 January 2026
  • Trinity By Karma construction site, inspection photo 3, 6 January 2026
  • Trinity By Karma construction site, inspection photo 4, 6 January 2026

2 September 2025

14%+12 pts

  • Trinity By Karma construction site, inspection photo 1, 2 September 2025
  • Trinity By Karma construction site, inspection photo 2, 2 September 2025
  • Trinity By Karma construction site, inspection photo 3, 2 September 2025
  • Trinity By Karma construction site, inspection photo 4, 2 September 2025

13 March 2025

1.6%+1.6 pts

  • Trinity By Karma construction site, inspection photo 1, 13 March 2025
  • Trinity By Karma construction site, inspection photo 2, 13 March 2025
  • Trinity By Karma construction site, inspection photo 3, 13 March 2025
  • Trinity By Karma construction site, inspection photo 4, 13 March 2025

12 November 2024

0%

  • Trinity By Karma construction site, inspection photo 1, 12 November 2024
  • Trinity By Karma construction site, inspection photo 2, 12 November 2024

22 January 2024

0%

  • Trinity By Karma construction site, inspection photo 1, 22 January 2024
  • Trinity By Karma construction site, inspection photo 2, 22 January 2024
  • Trinity By Karma construction site, inspection photo 3, 22 January 2024
  • Trinity By Karma construction site, inspection photo 4, 22 January 2024

All 44 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Karma Realty Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Trinity By Karma?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Trinity By Karma handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Trinity By Karma?
Trinity By Karma was 31% built at the site inspection on 30 September 2026. The site has been inspected 7 times since January 2024. The Land Department took 44 site photos at its inspections.
Is Trinity By Karma delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Trinity By Karma?
The registered developer is Karma Realty Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Trinity By Karma?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.