Aryene Greens construction progress

Aryene Greens in Arjan was registered to complete in November 2022 and is still under construction. At the last site inspection, in April 2026, it was 80% built. The developer is Diamond Star Real Estate Development.

80%

Built, at the site inspection of 2 April 2026

48 months past its registered completion date

Registered completion date
November 2022
Construction started
February 2009
First registered
February 2009
Developer
Diamond Star Real Estate Development
Community
Arjan
Units
125
Escrow bank
Mashreq Bank
Name in Arabic
أرين جرينز
Project number
474
Site inspections
14

Schedule

Aryene Greens was registered to complete in November 2022, 48 months ago, and is still under construction. The inspections on record are too close together or show no gain, so there is no pace to project a finish from.

0%25%50%75%100%201020132016201920222025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 April 2026

80%

  • Aryene Greens construction site, inspection photo 1, 2 April 2026
  • Aryene Greens construction site, inspection photo 2, 2 April 2026
  • Aryene Greens construction site, inspection photo 3, 2 April 2026
  • Aryene Greens construction site, inspection photo 4, 2 April 2026

23 October 2025

80%

  • Aryene Greens construction site, inspection photo 1, 23 October 2025
  • Aryene Greens construction site, inspection photo 2, 23 October 2025
  • Aryene Greens construction site, inspection photo 3, 23 October 2025
  • Aryene Greens construction site, inspection photo 4, 23 October 2025

8 November 2024

80%+6.0 pts

  • Aryene Greens construction site, inspection photo 1, 8 November 2024
  • Aryene Greens construction site, inspection photo 2, 8 November 2024
  • Aryene Greens construction site, inspection photo 3, 8 November 2024
  • Aryene Greens construction site, inspection photo 4, 8 November 2024

17 August 2022

74%+1.1 pts

  • Aryene Greens construction site, inspection photo 1, 17 August 2022
  • Aryene Greens construction site, inspection photo 2, 17 August 2022
  • Aryene Greens construction site, inspection photo 3, 17 August 2022
  • Aryene Greens construction site, inspection photo 4, 17 August 2022

10 June 2022

73%+1.8 pts

  • Aryene Greens construction site, inspection photo 1, 10 June 2022
  • Aryene Greens construction site, inspection photo 2, 10 June 2022
  • Aryene Greens construction site, inspection photo 3, 10 June 2022
  • Aryene Greens construction site, inspection photo 4, 10 June 2022

20 December 2021

71%+0.2 pts

  • Aryene Greens construction site, inspection photo 1, 20 December 2021
  • Aryene Greens construction site, inspection photo 2, 20 December 2021
  • Aryene Greens construction site, inspection photo 3, 20 December 2021
  • Aryene Greens construction site, inspection photo 4, 20 December 2021

28 June 2021

71%+10.0 pts

  • Aryene Greens construction site, inspection photo 1, 28 June 2021
  • Aryene Greens construction site, inspection photo 2, 28 June 2021
  • Aryene Greens construction site, inspection photo 3, 28 June 2021
  • Aryene Greens construction site, inspection photo 4, 28 June 2021

25 August 2020

61%+3.0 pts

  • Aryene Greens construction site, inspection photo 1, 25 August 2020
  • Aryene Greens construction site, inspection photo 2, 25 August 2020
  • Aryene Greens construction site, inspection photo 3, 25 August 2020
  • Aryene Greens construction site, inspection photo 4, 25 August 2020

18 June 2019

58%+6.0 pts

  • Aryene Greens construction site, inspection photo 1, 18 June 2019
  • Aryene Greens construction site, inspection photo 2, 18 June 2019
  • Aryene Greens construction site, inspection photo 3, 18 June 2019
  • Aryene Greens construction site, inspection photo 4, 18 June 2019

7 November 2017

52%+15 pts

  • Aryene Greens construction site, inspection photo 1, 7 November 2017
  • Aryene Greens construction site, inspection photo 2, 7 November 2017
  • Aryene Greens construction site, inspection photo 3, 7 November 2017
  • Aryene Greens construction site, inspection photo 4, 7 November 2017

All 118 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Own a unit in Aryene Greens?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Aryene Greens handover date?
The registered completion date was November 2022, and the register still lists Aryene Greens as under construction. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Aryene Greens?
Aryene Greens was 80% built at the site inspection on 2 April 2026. The site has been inspected 14 times since October 2012. The Land Department took 118 site photos at its inspections.
Is Aryene Greens delayed?
Yes. Its registered completion date of November 2022 has passed and the project is still listed as under construction.
Who is building Aryene Greens?
The registered developer is Diamond Star Real Estate Development.
Which bank holds the escrow account for Aryene Greens?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.