Aryene Greens construction progress
Aryene Greens in Arjan was registered to complete in November 2022 and is still under construction. At the last site inspection, in April 2026, it was 80% built. The developer is Diamond Star Real Estate Development.
80%
Built, at the site inspection of 2 April 2026
48 months past its registered completion date
- Registered completion date
- November 2022
- Construction started
- February 2009
- First registered
- February 2009
- Developer
- Diamond Star Real Estate Development
- Community
- Arjan
- Units
- 125
- Escrow bank
- Mashreq Bank
- Name in Arabic
- أرين جرينز
- Project number
- 474
- Site inspections
- 14
Schedule
Aryene Greens was registered to complete in November 2022, 48 months ago, and is still under construction. The inspections on record are too close together or show no gain, so there is no pace to project a finish from.
Site inspections
2 April 2026
80%
23 October 2025
80%
8 November 2024
80%+6.0 pts
17 August 2022
74%+1.1 pts
10 June 2022
73%+1.8 pts
20 December 2021
71%+0.2 pts
28 June 2021
71%+10.0 pts
25 August 2020
61%+3.0 pts
18 June 2019
58%+6.0 pts
7 November 2017
52%+15 pts
Context
Arjan has 23 projects under construction, 48% built on average.
Own a unit in Aryene Greens?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Aryene Greens handover date?
- The registered completion date was November 2022, and the register still lists Aryene Greens as under construction. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Aryene Greens?
- Aryene Greens was 80% built at the site inspection on 2 April 2026. The site has been inspected 14 times since October 2012. The Land Department took 118 site photos at its inspections.
- Is Aryene Greens delayed?
- Yes. Its registered completion date of November 2022 has passed and the project is still listed as under construction.
- Who is building Aryene Greens?
- The registered developer is Diamond Star Real Estate Development.
- Which bank holds the escrow account for Aryene Greens?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Elano By Oro24Nearby in Arjan. 70%, Due October 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)