Parkside Boulevard construction progress

The registered completion date for Parkside Boulevard in Arjan is December 2027. At the last site inspection, in October 2026, it was 60% built. The developer is Tabeer Real Estate Development.

60%

Built, at the site inspection of 28 October 2026

On pace for its date

Registered completion date
December 2027
Finish at recent pace
December 2027
Construction started
November 2024
First registered
January 2025
Community
Arjan
Units
171
Escrow bank
First Abu Dhabi Bank
Name in Arabic
باركسايد بوليفارد
Project number
3326
Site inspections
5

Schedule

Since October 2025 Parkside Boulevard has added about 3.0 points a month. That puts 100% around December 2027, within three months of its registered completion date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

60%+8.4 pts

  • Parkside Boulevard construction site, inspection photo 1, 28 October 2026
  • Parkside Boulevard construction site, inspection photo 2, 28 October 2026
  • Parkside Boulevard construction site, inspection photo 3, 28 October 2026
  • Parkside Boulevard construction site, inspection photo 4, 28 October 2026

20 May 2026

52%+28 pts

  • Parkside Boulevard construction site, inspection photo 1, 20 May 2026
  • Parkside Boulevard construction site, inspection photo 2, 20 May 2026
  • Parkside Boulevard construction site, inspection photo 3, 20 May 2026
  • Parkside Boulevard construction site, inspection photo 4, 20 May 2026

31 October 2025

24%+10 pts

  • Parkside Boulevard construction site, inspection photo 1, 31 October 2025
  • Parkside Boulevard construction site, inspection photo 2, 31 October 2025
  • Parkside Boulevard construction site, inspection photo 3, 31 October 2025
  • Parkside Boulevard construction site, inspection photo 4, 31 October 2025

12 August 2025

14%+13 pts

  • Parkside Boulevard construction site, inspection photo 1, 12 August 2025
  • Parkside Boulevard construction site, inspection photo 2, 12 August 2025
  • Parkside Boulevard construction site, inspection photo 3, 12 August 2025
  • Parkside Boulevard construction site, inspection photo 4, 12 August 2025

11 December 2024

1.0%

  • Parkside Boulevard construction site, inspection photo 1, 11 December 2024
  • Parkside Boulevard construction site, inspection photo 2, 11 December 2024
  • Parkside Boulevard construction site, inspection photo 3, 11 December 2024

All 39 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Tabeer Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Parkside Boulevard?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Parkside Boulevard handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Parkside Boulevard?
Parkside Boulevard was 60% built at the site inspection on 28 October 2026. The site has been inspected 5 times since December 2024. The Land Department took 39 site photos at its inspections.
Is Parkside Boulevard delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2027.
Who is building Parkside Boulevard?
The registered developer is Tabeer Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Parkside Boulevard?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.