Marquis One construction progress

The registered completion date for Marquis One in Arjan is December 2028. At the last site inspection, in October 2026, it was 0.3% built. The developer is Marquis Home Developer.

0.3%

Built, at the site inspection of 19 October 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
January 2231
Construction started
October 2025
First registered
September 2025
Community
Arjan
Units
489
Escrow bank
The National Bank of Fujairah
Name in Arabic
ماركيز وان
Project number
3702
Site inspections
3

Schedule

Between March 2026 and October 2026 the site added about 0.0 points a month. At that rate it would finish around January 2231, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 October 2026

0.3%+0.3 pts

  • Marquis One construction site, inspection photo 1, 19 October 2026
  • Marquis One construction site, inspection photo 2, 19 October 2026
  • Marquis One construction site, inspection photo 3, 19 October 2026

16 March 2026

0%

  • Marquis One construction site, inspection photo 1, 16 March 2026
  • Marquis One construction site, inspection photo 2, 16 March 2026

22 April 2025

0%

  • Marquis One construction site, inspection photo 1, 22 April 2025
  • Marquis One construction site, inspection photo 2, 22 April 2025

All 7 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Marquis Home Developer has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Marquis One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Marquis One handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2231. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Marquis One?
Marquis One was 0.3% built at the site inspection on 19 October 2026. The site has been inspected 3 times since April 2025. The Land Department took 7 site photos at its inspections.
Is Marquis One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Marquis One?
The registered developer is Marquis Home Developer. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Marquis One?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.