Samana Skyros construction progress

Samana Skyros in Arjan was registered to complete in April 2026 and is still under construction. At the last site inspection, in September 2026, it was 71% built. The developer is Samana Signature Real Estate Developments.

71%

Built, at the site inspection of 29 September 2026

7 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
July 2027
Construction started
November 2023
First registered
June 2023
Community
Arjan
Units
441
Escrow bank
Emirates NBD
Name in Arabic
سامانا سكايروز
Project number
2608
Site inspections
8

Schedule

Samana Skyros was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 September 2026

71%+11 pts

  • Samana Skyros construction site, inspection photo 1, 29 September 2026
  • Samana Skyros construction site, inspection photo 2, 29 September 2026
  • Samana Skyros construction site, inspection photo 3, 29 September 2026
  • Samana Skyros construction site, inspection photo 4, 29 September 2026

8 June 2026

60%+10 pts

  • Samana Skyros construction site, inspection photo 1, 8 June 2026
  • Samana Skyros construction site, inspection photo 2, 8 June 2026
  • Samana Skyros construction site, inspection photo 3, 8 June 2026
  • Samana Skyros construction site, inspection photo 4, 8 June 2026

5 February 2026

50%+12 pts

  • Samana Skyros construction site, inspection photo 1, 5 February 2026
  • Samana Skyros construction site, inspection photo 2, 5 February 2026
  • Samana Skyros construction site, inspection photo 3, 5 February 2026
  • Samana Skyros construction site, inspection photo 4, 5 February 2026

15 November 2025

38%+15 pts

  • Samana Skyros construction site, inspection photo 1, 15 November 2025
  • Samana Skyros construction site, inspection photo 2, 15 November 2025
  • Samana Skyros construction site, inspection photo 3, 15 November 2025
  • Samana Skyros construction site, inspection photo 4, 15 November 2025

16 July 2025

23%+10 pts

  • Samana Skyros construction site, inspection photo 1, 16 July 2025
  • Samana Skyros construction site, inspection photo 2, 16 July 2025
  • Samana Skyros construction site, inspection photo 3, 16 July 2025
  • Samana Skyros construction site, inspection photo 4, 16 July 2025

26 February 2025

13%+12 pts

  • Samana Skyros construction site, inspection photo 1, 26 February 2025
  • Samana Skyros construction site, inspection photo 2, 26 February 2025
  • Samana Skyros construction site, inspection photo 3, 26 February 2025
  • Samana Skyros construction site, inspection photo 4, 26 February 2025

21 May 2024

0.6%+0.6 pts

  • Samana Skyros construction site, inspection photo 1, 21 May 2024
  • Samana Skyros construction site, inspection photo 2, 21 May 2024
  • Samana Skyros construction site, inspection photo 3, 21 May 2024
  • Samana Skyros construction site, inspection photo 4, 21 May 2024

16 March 2023

0%

  • Samana Skyros construction site, inspection photo 1, 16 March 2023

All 55 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Samana Skyros?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Skyros handover date?
The registered completion date was April 2026, and the register still lists Samana Skyros as under construction. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Skyros?
Samana Skyros was 71% built at the site inspection on 29 September 2026. The site has been inspected 8 times since March 2023. The Land Department took 55 site photos at its inspections.
Is Samana Skyros delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Samana Skyros?
The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Skyros?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.