Samana Skyros construction progress
Samana Skyros in Arjan was registered to complete in April 2026 and is still under construction. At the last site inspection, in September 2026, it was 71% built. The developer is Samana Signature Real Estate Developments.
71%
Built, at the site inspection of 29 September 2026
7 months past its registered completion date
- Registered completion date
- April 2026
- Finish at recent pace
- July 2027
- Construction started
- November 2023
- First registered
- June 2023
- Community
- Arjan
- Units
- 441
- Escrow bank
- Emirates NBD
- Name in Arabic
- سامانا سكايروز
- Project number
- 2608
- Site inspections
- 8
Schedule
Samana Skyros was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around July 2027.
Site inspections
29 September 2026
71%+11 pts
8 June 2026
60%+10 pts
5 February 2026
50%+12 pts
15 November 2025
38%+15 pts
16 July 2025
23%+10 pts
26 February 2025
13%+12 pts
21 May 2024
0.6%+0.6 pts
16 March 2023
0%
Context
Arjan has 23 projects under construction, 48% built on average.
Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Samana Skyros?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Skyros handover date?
- The registered completion date was April 2026, and the register still lists Samana Skyros as under construction. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samana Skyros?
- Samana Skyros was 71% built at the site inspection on 29 September 2026. The site has been inspected 8 times since March 2023. The Land Department took 55 site photos at its inspections.
- Is Samana Skyros delayed?
- Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
- Who is building Samana Skyros?
- The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Skyros?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana Lake ViewsAlso by Samana Signature Real Estate Developments. 23%.
- Samana Lake Views 2Also by Samana Signature Real Estate Developments. 12%.
- Samana Barari LagoonsAlso by Samana Signature Real Estate Developments. 17%, Due March 2028.
- Samana ParkvilleAlso by Samana Signature Real Estate Developments. 14%, Due September 2028.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Elano By Oro24Nearby in Arjan. 70%, Due October 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)