Samana Skyros construction progress

Samana Skyros in Arjan is 71% built at the Land Department inspection of September 2026. Developer Samana Signature Real Estate Developments. Completion registered for April 2026.

71%

Built, at the Land Department site inspection of 29 September 2026

5 months past its registered completion date

Completion date (Land Department)
April 2026
Finish at recent pace
July 2027
Construction started
November 2023
Registered with the Land Department
June 2023
Community
Arjan
Units
441
Escrow bank
Emirates NBD
Name in Arabic
سامانا سكايروز
Land Department project number
2608
Land Department site inspections
8

Schedule

Samana Skyros was registered to complete in April 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 September 2026

71%+11 pts

  • Samana Skyros construction site, Land Department inspection photo 1, 29 September 2026
  • Samana Skyros construction site, Land Department inspection photo 2, 29 September 2026
  • Samana Skyros construction site, Land Department inspection photo 3, 29 September 2026
  • Samana Skyros construction site, Land Department inspection photo 4, 29 September 2026

8 June 2026

60%+10 pts

  • Samana Skyros construction site, Land Department inspection photo 1, 8 June 2026
  • Samana Skyros construction site, Land Department inspection photo 2, 8 June 2026
  • Samana Skyros construction site, Land Department inspection photo 3, 8 June 2026
  • Samana Skyros construction site, Land Department inspection photo 4, 8 June 2026

5 February 2026

50%+12 pts

  • Samana Skyros construction site, Land Department inspection photo 1, 5 February 2026
  • Samana Skyros construction site, Land Department inspection photo 2, 5 February 2026
  • Samana Skyros construction site, Land Department inspection photo 3, 5 February 2026
  • Samana Skyros construction site, Land Department inspection photo 4, 5 February 2026

15 November 2025

38%+15 pts

  • Samana Skyros construction site, Land Department inspection photo 1, 15 November 2025
  • Samana Skyros construction site, Land Department inspection photo 2, 15 November 2025
  • Samana Skyros construction site, Land Department inspection photo 3, 15 November 2025
  • Samana Skyros construction site, Land Department inspection photo 4, 15 November 2025

16 July 2025

23%+10 pts

  • Samana Skyros construction site, Land Department inspection photo 1, 16 July 2025
  • Samana Skyros construction site, Land Department inspection photo 2, 16 July 2025
  • Samana Skyros construction site, Land Department inspection photo 3, 16 July 2025
  • Samana Skyros construction site, Land Department inspection photo 4, 16 July 2025

26 February 2025

13%+12 pts

  • Samana Skyros construction site, Land Department inspection photo 1, 26 February 2025
  • Samana Skyros construction site, Land Department inspection photo 2, 26 February 2025
  • Samana Skyros construction site, Land Department inspection photo 3, 26 February 2025
  • Samana Skyros construction site, Land Department inspection photo 4, 26 February 2025

21 May 2024

0.6%+0.6 pts

  • Samana Skyros construction site, Land Department inspection photo 1, 21 May 2024
  • Samana Skyros construction site, Land Department inspection photo 2, 21 May 2024
  • Samana Skyros construction site, Land Department inspection photo 3, 21 May 2024
  • Samana Skyros construction site, Land Department inspection photo 4, 21 May 2024

16 March 2023

0%

  • Samana Skyros construction site, Land Department inspection photo 1, 16 March 2023

All 55 site photos, by inspection date

Context

Arjan has 23 projects under construction, 46% built on average. Samana Skyros is ahead of that average.

Samana Signature Real Estate Developments has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Samana Skyros?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Samana Skyros be completed?
The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Samana Skyros is built?
71%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 8 times since March 2023.
Is Samana Skyros delayed?
Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
Who is building Samana Skyros?
The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Skyros?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.