Samana Skyros construction progress
Samana Skyros in Arjan is 71% built at the Land Department inspection of September 2026. Developer Samana Signature Real Estate Developments. Completion registered for April 2026.
71%
Built, at the Land Department site inspection of 29 September 2026
5 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- July 2027
- Construction started
- November 2023
- Registered with the Land Department
- June 2023
- Community
- Arjan
- Units
- 441
- Escrow bank
- Emirates NBD
- Name in Arabic
- سامانا سكايروز
- Land Department project number
- 2608
- Land Department site inspections
- 8
Schedule
Samana Skyros was registered to complete in April 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around July 2027.
Site inspections
29 September 2026
71%+11 pts
8 June 2026
60%+10 pts
5 February 2026
50%+12 pts
15 November 2025
38%+15 pts
16 July 2025
23%+10 pts
26 February 2025
13%+12 pts
21 May 2024
0.6%+0.6 pts
16 March 2023
0%
Context
Arjan has 23 projects under construction, 46% built on average. Samana Skyros is ahead of that average.
Samana Signature Real Estate Developments has 12 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Samana Skyros?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Samana Skyros be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Samana Skyros is built?
- 71%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 8 times since March 2023.
- Is Samana Skyros delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Samana Skyros?
- The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Skyros?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana Lake ViewsAlso by Samana Signature Real Estate Developments. 23%.
- Samana Lake Views 2Also by Samana Signature Real Estate Developments. 8.9%.
- Samana Barari LagoonsAlso by Samana Signature Real Estate Developments. 12%.
- Samana ParkvilleAlso by Samana Signature Real Estate Developments. 5.1%, Due September 2028.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 80%, Due April 2026, passed.
- Elano By Oro24Nearby in Arjan. 70%, Due October 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.