Vincitore Volare construction progress

Vincitore Volare in Arjan is 63% built at the Land Department inspection of April 2026. Developer Vincitore Premium Real Estate Development. Completion registered for June 2025.

63%

Built, at the Land Department site inspection of 22 April 2026

16 months past its registered completion date

Completion date (Land Department)
June 2025
Finish at recent pace
March 2027
Construction started
December 2022
Registered with the Land Department
December 2022
Community
Arjan
Units
415
Escrow bank
Mashreq Bank
Name in Arabic
فينسيتور فولاري
Land Department project number
2499
Land Department site inspections
8

Schedule

Vincitore Volare was registered to complete in June 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 3.4 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 April 2026

63%+12 pts

  • Vincitore Volare construction site, Land Department inspection photo 1, 22 April 2026
  • Vincitore Volare construction site, Land Department inspection photo 2, 22 April 2026
  • Vincitore Volare construction site, Land Department inspection photo 3, 22 April 2026
  • Vincitore Volare construction site, Land Department inspection photo 4, 22 April 2026

15 December 2025

51%+19 pts

  • Vincitore Volare construction site, Land Department inspection photo 1, 15 December 2025
  • Vincitore Volare construction site, Land Department inspection photo 2, 15 December 2025
  • Vincitore Volare construction site, Land Department inspection photo 3, 15 December 2025
  • Vincitore Volare construction site, Land Department inspection photo 4, 15 December 2025

21 July 2025

32%+12 pts

  • Vincitore Volare construction site, Land Department inspection photo 1, 21 July 2025
  • Vincitore Volare construction site, Land Department inspection photo 2, 21 July 2025
  • Vincitore Volare construction site, Land Department inspection photo 3, 21 July 2025
  • Vincitore Volare construction site, Land Department inspection photo 4, 21 July 2025

16 December 2024

21%+11 pts

  • Vincitore Volare construction site, Land Department inspection photo 1, 16 December 2024
  • Vincitore Volare construction site, Land Department inspection photo 2, 16 December 2024
  • Vincitore Volare construction site, Land Department inspection photo 3, 16 December 2024
  • Vincitore Volare construction site, Land Department inspection photo 4, 16 December 2024

26 June 2024

10%+4.0 pts

  • Vincitore Volare construction site, Land Department inspection photo 1, 26 June 2024
  • Vincitore Volare construction site, Land Department inspection photo 2, 26 June 2024
  • Vincitore Volare construction site, Land Department inspection photo 3, 26 June 2024
  • Vincitore Volare construction site, Land Department inspection photo 4, 26 June 2024

6 November 2023

6.0%+1.9 pts

  • Vincitore Volare construction site, Land Department inspection photo 1, 6 November 2023
  • Vincitore Volare construction site, Land Department inspection photo 2, 6 November 2023
  • Vincitore Volare construction site, Land Department inspection photo 3, 6 November 2023
  • Vincitore Volare construction site, Land Department inspection photo 4, 6 November 2023

17 April 2023

4.1%+3.9 pts

  • Vincitore Volare construction site, Land Department inspection photo 1, 17 April 2023
  • Vincitore Volare construction site, Land Department inspection photo 2, 17 April 2023
  • Vincitore Volare construction site, Land Department inspection photo 3, 17 April 2023
  • Vincitore Volare construction site, Land Department inspection photo 4, 17 April 2023

31 October 2022

0.1%

  • Vincitore Volare construction site, Land Department inspection photo 1, 31 October 2022
  • Vincitore Volare construction site, Land Department inspection photo 2, 31 October 2022
  • Vincitore Volare construction site, Land Department inspection photo 3, 31 October 2022
  • Vincitore Volare construction site, Land Department inspection photo 4, 31 October 2022

All 64 site photos, by inspection date

Context

Arjan has 23 projects under construction, 46% built on average.

Vincitore Premium Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Vincitore Volare?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vincitore Volare be completed?
The completion date registered with the Dubai Land Department is June 2025. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vincitore Volare is built?
63%, measured at the Land Department site inspection on 22 April 2026. The Land Department engineers have inspected the site 8 times since October 2022.
Is Vincitore Volare delayed?
Yes. Its registered completion date of June 2025 has passed and the Land Department still lists it as under construction.
Who is building Vincitore Volare?
The registered developer is Vincitore Premium Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Vincitore Volare?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.