Vincitore Volare construction progress

Vincitore Volare in Arjan was registered to complete in June 2025 and is still under construction. At the last site inspection, in April 2026, it was 63% built. The developer is Vincitore Premium Real Estate Development.

63%

Built, at the site inspection of 22 April 2026

18 months past its registered completion date

Registered completion date
June 2025
Finish at recent pace
March 2027
Construction started
December 2022
First registered
December 2022
Community
Arjan
Units
415
Escrow bank
Mashreq Bank
Name in Arabic
فينسيتور فولاري
Project number
2499
Site inspections
8

Schedule

Vincitore Volare was registered to complete in June 2025, 18 months ago, and is still under construction. Over the last year of inspections it has added about 3.4 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 April 2026

63%+12 pts

  • Vincitore Volare construction site, inspection photo 1, 22 April 2026
  • Vincitore Volare construction site, inspection photo 2, 22 April 2026
  • Vincitore Volare construction site, inspection photo 3, 22 April 2026
  • Vincitore Volare construction site, inspection photo 4, 22 April 2026

15 December 2025

51%+19 pts

  • Vincitore Volare construction site, inspection photo 1, 15 December 2025
  • Vincitore Volare construction site, inspection photo 2, 15 December 2025
  • Vincitore Volare construction site, inspection photo 3, 15 December 2025
  • Vincitore Volare construction site, inspection photo 4, 15 December 2025

21 July 2025

32%+12 pts

  • Vincitore Volare construction site, inspection photo 1, 21 July 2025
  • Vincitore Volare construction site, inspection photo 2, 21 July 2025
  • Vincitore Volare construction site, inspection photo 3, 21 July 2025
  • Vincitore Volare construction site, inspection photo 4, 21 July 2025

16 December 2024

21%+11 pts

  • Vincitore Volare construction site, inspection photo 1, 16 December 2024
  • Vincitore Volare construction site, inspection photo 2, 16 December 2024
  • Vincitore Volare construction site, inspection photo 3, 16 December 2024
  • Vincitore Volare construction site, inspection photo 4, 16 December 2024

26 June 2024

10%+4.0 pts

  • Vincitore Volare construction site, inspection photo 1, 26 June 2024
  • Vincitore Volare construction site, inspection photo 2, 26 June 2024
  • Vincitore Volare construction site, inspection photo 3, 26 June 2024
  • Vincitore Volare construction site, inspection photo 4, 26 June 2024

6 November 2023

6.0%+1.9 pts

  • Vincitore Volare construction site, inspection photo 1, 6 November 2023
  • Vincitore Volare construction site, inspection photo 2, 6 November 2023
  • Vincitore Volare construction site, inspection photo 3, 6 November 2023
  • Vincitore Volare construction site, inspection photo 4, 6 November 2023

17 April 2023

4.1%+3.9 pts

  • Vincitore Volare construction site, inspection photo 1, 17 April 2023
  • Vincitore Volare construction site, inspection photo 2, 17 April 2023
  • Vincitore Volare construction site, inspection photo 3, 17 April 2023
  • Vincitore Volare construction site, inspection photo 4, 17 April 2023

31 October 2022

0.1%

  • Vincitore Volare construction site, inspection photo 1, 31 October 2022
  • Vincitore Volare construction site, inspection photo 2, 31 October 2022
  • Vincitore Volare construction site, inspection photo 3, 31 October 2022
  • Vincitore Volare construction site, inspection photo 4, 31 October 2022

All 64 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Vincitore Premium Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Vincitore Volare?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vincitore Volare handover date?
The registered completion date was June 2025, and the register still lists Vincitore Volare as under construction. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vincitore Volare?
Vincitore Volare was 63% built at the site inspection on 22 April 2026. The site has been inspected 8 times since October 2022. The Land Department took 64 site photos at its inspections.
Is Vincitore Volare delayed?
Yes. Its registered completion date of June 2025 has passed and the project is still listed as under construction.
Who is building Vincitore Volare?
The registered developer is Vincitore Premium Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Vincitore Volare?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.