Vincitore Volare construction progress
Vincitore Volare in Arjan is 63% built at the Land Department inspection of April 2026. Developer Vincitore Premium Real Estate Development. Completion registered for June 2025.
63%
Built, at the Land Department site inspection of 22 April 2026
16 months past its registered completion date
- Completion date (Land Department)
- June 2025
- Finish at recent pace
- March 2027
- Construction started
- December 2022
- Registered with the Land Department
- December 2022
- Community
- Arjan
- Units
- 415
- Escrow bank
- Mashreq Bank
- Name in Arabic
- فينسيتور فولاري
- Land Department project number
- 2499
- Land Department site inspections
- 8
Schedule
Vincitore Volare was registered to complete in June 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 3.4 points a month. Kept at that rate, the site would reach 100% around March 2027.
Site inspections
22 April 2026
63%+12 pts
15 December 2025
51%+19 pts
21 July 2025
32%+12 pts
16 December 2024
21%+11 pts
26 June 2024
10%+4.0 pts
6 November 2023
6.0%+1.9 pts
17 April 2023
4.1%+3.9 pts
31 October 2022
0.1%
Context
Arjan has 23 projects under construction, 46% built on average.
Vincitore Premium Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Vincitore Volare?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Vincitore Volare be completed?
- The completion date registered with the Dubai Land Department is June 2025. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Vincitore Volare is built?
- 63%, measured at the Land Department site inspection on 22 April 2026. The Land Department engineers have inspected the site 8 times since October 2022.
- Is Vincitore Volare delayed?
- Yes. Its registered completion date of June 2025 has passed and the Land Department still lists it as under construction.
- Who is building Vincitore Volare?
- The registered developer is Vincitore Premium Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Vincitore Volare?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vincitore Dolce VitaAlso by Vincitore Premium Real Estate Development. 22%.
- Vincitore Wellness EstateAlso by Vincitore Premium Real Estate Development. 0%, Due February 2030.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Samana Mykonos SignatureNearby in Arjan. 80%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Elano By Oro24Nearby in Arjan. 70%, Due October 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)