The Central Downtown construction progress
The registered completion date for The Central Downtown in Arjan is March 2028. At the last site inspection, in April 2026, it was 10% built. The developer is Aqua Properties.
10%
Built, at the site inspection of 21 April 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- May 2039
- Construction started
- November 2023
- First registered
- January 2024
- Developer
- Aqua Properties
- Community
- Arjan
- Units
- 1,254
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- وسط البلد
- Project number
- 2861
- Site inspections
- 4
Schedule
Between May 2025 and April 2026 the site added about 0.6 points a month. At that rate it would finish around May 2039, more than three months after its registered date of March 2028.
Site inspections
21 April 2026
10%+6.3 pts
22 May 2025
4.2%+3.5 pts
15 November 2024
0.7%+0.7 pts
24 November 2023
0%
Context
Arjan has 23 projects under construction, 48% built on average.
Aqua Properties has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in The Central Downtown?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Central Downtown handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Central Downtown?
- The Central Downtown was 10% built at the site inspection on 21 April 2026. The site has been inspected 4 times since November 2023. The Land Department took 21 site photos at its inspections.
- Is The Central Downtown delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building The Central Downtown?
- The registered developer is Aqua Properties. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for The Central Downtown?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Community Motor CityAlso by Aqua Properties. 95%, Due October 2025, passed.
- The Community - Sports ArenaAlso by Aqua Properties. 22%, Due October 2027.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)