Skip to content

The Central Downtown construction progress

The registered completion date for The Central Downtown in Arjan is March 2028. At the last site inspection, in April 2026, it was 10% built. The developer is Aqua Properties.

10%

Built, at the site inspection of 21 April 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
May 2039
Construction started
November 2023
First registered
January 2024
Community
Arjan
Units
1,254
Escrow bank
First Abu Dhabi Bank
Name in Arabic
وسط البلد
Project number
2861
Site inspections
4

Schedule

Between May 2025 and April 2026 the site added about 0.6 points a month. At that rate it would finish around May 2039, more than three months after its registered date of March 2028.

0%25%50%75%100%20242025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 April 2026

10%+6.3 pts

  • The Central Downtown construction site, inspection photo 1, 21 April 2026
  • The Central Downtown construction site, inspection photo 2, 21 April 2026
  • The Central Downtown construction site, inspection photo 3, 21 April 2026
  • The Central Downtown construction site, inspection photo 4, 21 April 2026

22 May 2025

4.2%+3.5 pts

  • The Central Downtown construction site, inspection photo 1, 22 May 2025
  • The Central Downtown construction site, inspection photo 2, 22 May 2025
  • The Central Downtown construction site, inspection photo 3, 22 May 2025
  • The Central Downtown construction site, inspection photo 4, 22 May 2025

15 November 2024

0.7%+0.7 pts

  • The Central Downtown construction site, inspection photo 1, 15 November 2024
  • The Central Downtown construction site, inspection photo 2, 15 November 2024
  • The Central Downtown construction site, inspection photo 3, 15 November 2024
  • The Central Downtown construction site, inspection photo 4, 15 November 2024

24 November 2023

0%

  • The Central Downtown construction site, inspection photo 1, 24 November 2023
  • The Central Downtown construction site, inspection photo 2, 24 November 2023
  • The Central Downtown construction site, inspection photo 3, 24 November 2023

All 21 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Aqua Properties has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Central Downtown?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Central Downtown handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Central Downtown?
The Central Downtown was 10% built at the site inspection on 21 April 2026. The site has been inspected 4 times since November 2023. The Land Department took 21 site photos at its inspections.
Is The Central Downtown delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building The Central Downtown?
The registered developer is Aqua Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for The Central Downtown?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.