Elano By Oro24 construction progress
Elano By Oro24 in Arjan is 70% built at the Land Department inspection of September 2026. Developer Oro24 Real Estate Development. Completion registered for October 2025.
70%
Built, at the Land Department site inspection of 11 September 2026
12 months past its registered completion date
- Completion date (Land Department)
- October 2025
- Finish at recent pace
- June 2027
- Construction started
- April 2023
- Registered with the Land Department
- April 2023
- Developer
- Oro24 Real Estate Development
- Community
- Arjan
- Units
- 339
- Escrow bank
- Mashreq Bank
- Name in Arabic
- إيلانو من أورو 24
- Land Department project number
- 2620
- Land Department site inspections
- 8
Schedule
Elano By Oro24 was registered to complete in October 2025, 12 months ago, and is still under construction. Over the last year of inspections it has added about 3.4 points a month. Kept at that rate, the site would reach 100% around June 2027.
Site inspections
11 September 2026
70%+14 pts
24 April 2026
56%+16 pts
22 January 2026
40%+8.4 pts
6 October 2025
32%+9.9 pts
27 May 2025
22%+18 pts
20 March 2024
3.8%+1.1 pts
6 November 2023
2.7%+2.5 pts
1 August 2023
0.2%
Context
Arjan has 23 projects under construction, 46% built on average.
Oro24 Real Estate Development has 4 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Elano By Oro24?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Elano By Oro24 be completed?
- The completion date registered with the Dubai Land Department is October 2025. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Elano By Oro24 is built?
- 70%, measured at the Land Department site inspection on 11 September 2026. The Land Department engineers have inspected the site 8 times since August 2023.
- Is Elano By Oro24 delayed?
- Yes. Its registered completion date of October 2025 has passed and the Land Department still lists it as under construction.
- Who is building Elano By Oro24?
- The registered developer is Oro24 Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Elano By Oro24?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Levanto By Oro24Also by Oro24 Real Estate Development. 66%, Due December 2025, passed.
- Kyoto By Oro24Also by Oro24 Real Estate Development. 17%.
- Albero By Oro24Also by Oro24 Real Estate Development. 45%.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 80%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
%2520B-2%2C%2520Part-A%26B%2520(8).jpg&w=3840&q=75)
%2520Fencing%2520(2).jpg&w=3840&q=75)
%2520Elevation%2520(3).jpg&w=3840&q=75)
%2520L-1%2C%2520Part-A%26B%2520(19).jpg&w=3840&q=75)



.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)