The Lx construction progress
The registered completion date for The Lx in Arjan is August 2027. At the last site inspection, in June 2026, it was 4.9% built. The developer is Mulk Properties.
4.9%
Built, at the site inspection of 4 June 2026
Running behind its date
- Registered completion date
- August 2027
- Finish at recent pace
- July 2046
- Construction started
- June 2025
- First registered
- May 2025
- Developer
- Mulk Properties
- Community
- Arjan
- Units
- 80
- Escrow bank
- United Bank Limited
- Name in Arabic
- ذالكس
- Project number
- 3772
- Site inspections
- 2
Schedule
Between May 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around July 2046, more than three months after its registered date of August 2027.
Site inspections
4 June 2026
4.9%+4.9 pts
22 May 2025
0%
Context
Arjan has 23 projects under construction, 48% built on average.
Own a unit in The Lx?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Lx handover date?
- The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2046. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Lx?
- The Lx was 4.9% built at the site inspection on 4 June 2026. The site has been inspected 2 times since May 2025. The Land Department took 6 site photos at its inspections.
- Is The Lx delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building The Lx?
- The registered developer is Mulk Properties.
- Which bank holds the escrow account for The Lx?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)