Floarea Grande construction progress

Floarea Grande in Arjan is 48% built at the Land Department inspection of August 2026. Developer Mashriq Elite Real Estate Development. Completion registered for August 2027.

48%

Built, at the Land Department site inspection of 14 August 2026

On pace for its date

Completion date (Land Department)
August 2027
Finish at recent pace
September 2027
Construction started
February 2025
Registered with the Land Department
February 2025
Community
Arjan
Units
222
Escrow bank
Mashreq Bank
Name in Arabic
فلوريا جراند
Land Department project number
3494
Land Department site inspections
6

Schedule

Since October 2025 Floarea Grande has added about 3.9 points a month. That puts 100% around September 2027, within three months of its registered completion date of August 2027.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 August 2026

48%+14 pts

  • Floarea Grande construction site, Land Department inspection photo 1, 14 August 2026
  • Floarea Grande construction site, Land Department inspection photo 2, 14 August 2026
  • Floarea Grande construction site, Land Department inspection photo 3, 14 August 2026
  • Floarea Grande construction site, Land Department inspection photo 4, 14 August 2026

6 May 2026

34%+17 pts

  • Floarea Grande construction site, Land Department inspection photo 1, 6 May 2026
  • Floarea Grande construction site, Land Department inspection photo 2, 6 May 2026
  • Floarea Grande construction site, Land Department inspection photo 3, 6 May 2026
  • Floarea Grande construction site, Land Department inspection photo 4, 6 May 2026

29 January 2026

17%+7.7 pts

  • Floarea Grande construction site, Land Department inspection photo 1, 29 January 2026
  • Floarea Grande construction site, Land Department inspection photo 2, 29 January 2026
  • Floarea Grande construction site, Land Department inspection photo 3, 29 January 2026
  • Floarea Grande construction site, Land Department inspection photo 4, 29 January 2026

8 October 2025

9.0%+6.5 pts

  • Floarea Grande construction site, Land Department inspection photo 1, 8 October 2025
  • Floarea Grande construction site, Land Department inspection photo 2, 8 October 2025
  • Floarea Grande construction site, Land Department inspection photo 3, 8 October 2025
  • Floarea Grande construction site, Land Department inspection photo 4, 8 October 2025

29 May 2025

2.5%+2.5 pts

  • Floarea Grande construction site, Land Department inspection photo 1, 29 May 2025
  • Floarea Grande construction site, Land Department inspection photo 2, 29 May 2025
  • Floarea Grande construction site, Land Department inspection photo 3, 29 May 2025
  • Floarea Grande construction site, Land Department inspection photo 4, 29 May 2025

16 January 2025

0%

  • Floarea Grande construction site, Land Department inspection photo 1, 16 January 2025
  • Floarea Grande construction site, Land Department inspection photo 2, 16 January 2025
  • Floarea Grande construction site, Land Department inspection photo 3, 16 January 2025

All 44 site photos, by inspection date

Context

Arjan has 23 projects under construction, 46% built on average.

Mashriq Elite Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Floarea Grande?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Floarea Grande be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around September 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Floarea Grande is built?
48%, measured at the Land Department site inspection on 14 August 2026. The Land Department engineers have inspected the site 6 times since January 2025.
Is Floarea Grande delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of August 2027.
Who is building Floarea Grande?
The registered developer is Mashriq Elite Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Floarea Grande?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.