Butterfly construction progress

The registered completion date for Butterfly in Arjan is January 2029. At the last site inspection, in November 2026, it was 8.2% built. The developer is Desert Falcon Real Estate Development.

8.2%

Built, at the site inspection of 4 November 2026

Running behind its date

Registered completion date
January 2029
Finish at recent pace
November 2110
Construction started
January 2025
First registered
August 2024
Developer
Desert Falcon Real Estate Development
Community
Arjan
Units
596
Escrow bank
Emirates NBD
Name in Arabic
بترفلاى ريسيدينس
Project number
3060
Site inspections
3

Schedule

Between May 2026 and November 2026 the site added about 0.1 points a month. At that rate it would finish around November 2110, more than three months after its registered date of January 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 November 2026

8.2%+0.5 pts

  • Butterfly construction site, inspection photo 1, 4 November 2026
  • Butterfly construction site, inspection photo 2, 4 November 2026
  • Butterfly construction site, inspection photo 3, 4 November 2026
  • Butterfly construction site, inspection photo 4, 4 November 2026

21 May 2026

7.7%+7.7 pts

  • Butterfly construction site, inspection photo 1, 21 May 2026
  • Butterfly construction site, inspection photo 2, 21 May 2026
  • Butterfly construction site, inspection photo 3, 21 May 2026
  • Butterfly construction site, inspection photo 4, 21 May 2026

2 July 2024

0%

  • Butterfly construction site, inspection photo 1, 2 July 2024
  • Butterfly construction site, inspection photo 2, 2 July 2024

All 11 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Own a unit in Butterfly?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Butterfly handover date?
The registered completion date is January 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2110. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Butterfly?
Butterfly was 8.2% built at the site inspection on 4 November 2026. The site has been inspected 3 times since July 2024. The Land Department took 11 site photos at its inspections.
Is Butterfly delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
Who is building Butterfly?
The registered developer is Desert Falcon Real Estate Development.
Which bank holds the escrow account for Butterfly?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.