Butterfly construction progress
The registered completion date for Butterfly in Arjan is January 2029. At the last site inspection, in November 2026, it was 8.2% built. The developer is Desert Falcon Real Estate Development.
8.2%
Built, at the site inspection of 4 November 2026
Running behind its date
- Registered completion date
- January 2029
- Finish at recent pace
- November 2110
- Construction started
- January 2025
- First registered
- August 2024
- Developer
- Desert Falcon Real Estate Development
- Community
- Arjan
- Units
- 596
- Escrow bank
- Emirates NBD
- Name in Arabic
- بترفلاى ريسيدينس
- Project number
- 3060
- Site inspections
- 3
Schedule
Between May 2026 and November 2026 the site added about 0.1 points a month. At that rate it would finish around November 2110, more than three months after its registered date of January 2029.
Site inspections
4 November 2026
8.2%+0.5 pts
21 May 2026
7.7%+7.7 pts
2 July 2024
0%
Context
Arjan has 23 projects under construction, 48% built on average.
Own a unit in Butterfly?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Butterfly handover date?
- The registered completion date is January 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2110. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Butterfly?
- Butterfly was 8.2% built at the site inspection on 4 November 2026. The site has been inspected 3 times since July 2024. The Land Department took 11 site photos at its inspections.
- Is Butterfly delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
- Who is building Butterfly?
- The registered developer is Desert Falcon Real Estate Development.
- Which bank holds the escrow account for Butterfly?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 86%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)