Samana Mykonos Signature construction progress
Samana Mykonos Signature in Arjan is 80% built at the Land Department inspection of May 2026. Developer Samana International Real Estate Development. Completion registered for April 2026.
80%
Built, at the Land Department site inspection of 14 May 2026
5 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- October 2026
- Construction started
- October 2023
- Registered with the Land Department
- June 2023
- Community
- Arjan
- Units
- 300
- Escrow bank
- Emirates NBD
- Name in Arabic
- سامانا ميكونوس سيجنيتشر
- Land Department project number
- 2587
- Land Department site inspections
- 8
Schedule
Samana Mykonos Signature was registered to complete in April 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 3.8 points a month. Kept at that rate, the site would reach 100% around October 2026.
Site inspections
14 May 2026
80%+7.8 pts
22 January 2026
73%+23 pts
2 October 2025
49%+5.0 pts
29 July 2025
44%+13 pts
26 March 2025
31%+16 pts
23 October 2024
15%+13 pts
8 May 2024
1.9%+1.9 pts
2 March 2023
0%
Context
Arjan has 23 projects under construction, 46% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Mykonos Signature?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Samana Mykonos Signature be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around October 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Samana Mykonos Signature is built?
- 80%, measured at the Land Department site inspection on 14 May 2026. The Land Department engineers have inspected the site 8 times since March 2023.
- Is Samana Mykonos Signature delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Samana Mykonos Signature?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Mykonos Signature?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosAlso by Samana International Real Estate Development. 91%, Due April 2026, passed.
- Samana Ivy GardensAlso by Samana International Real Estate Development. 41%.
- Samana Golf ViewsAlso by Samana International Real Estate Development. 56%.
- Samana PortofinoAlso by Samana International Real Estate Development. 60%.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Elano By Oro24Nearby in Arjan. 70%, Due October 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)





















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)