One Beverly construction progress

The registered completion date for One Beverly in Arjan is December 2026. At the last site inspection, in May 2026, it was 73% built. The developer is H M B Homes Real Estate Development.

73%

Built, at the site inspection of 6 May 2026

On pace for its date

Registered completion date
December 2026
Finish at recent pace
October 2026
Construction started
December 2024
First registered
November 2024
Community
Arjan
Units
389
Escrow bank
Mashreq Bank
Name in Arabic
واحد بيفرلى
Project number
3163
Site inspections
6

Schedule

Since May 2025 One Beverly has added about 4.9 points a month. That puts 100% around October 2026, within three months of its registered completion date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 May 2026

73%+14 pts

  • One Beverly construction site, inspection photo 1, 6 May 2026
  • One Beverly construction site, inspection photo 2, 6 May 2026
  • One Beverly construction site, inspection photo 3, 6 May 2026
  • One Beverly construction site, inspection photo 4, 6 May 2026

13 February 2026

59%+12 pts

  • One Beverly construction site, inspection photo 1, 13 February 2026
  • One Beverly construction site, inspection photo 2, 13 February 2026
  • One Beverly construction site, inspection photo 3, 13 February 2026
  • One Beverly construction site, inspection photo 4, 13 February 2026

23 October 2025

47%+22 pts

  • One Beverly construction site, inspection photo 1, 23 October 2025
  • One Beverly construction site, inspection photo 2, 23 October 2025
  • One Beverly construction site, inspection photo 3, 23 October 2025
  • One Beverly construction site, inspection photo 4, 23 October 2025

8 July 2025

25%+7.0 pts

  • One Beverly construction site, inspection photo 1, 8 July 2025
  • One Beverly construction site, inspection photo 2, 8 July 2025
  • One Beverly construction site, inspection photo 3, 8 July 2025
  • One Beverly construction site, inspection photo 4, 8 July 2025

27 May 2025

18%+18 pts

  • One Beverly construction site, inspection photo 1, 27 May 2025
  • One Beverly construction site, inspection photo 2, 27 May 2025
  • One Beverly construction site, inspection photo 3, 27 May 2025
  • One Beverly construction site, inspection photo 4, 27 May 2025

3 July 2024

0%

  • One Beverly construction site, inspection photo 1, 3 July 2024
  • One Beverly construction site, inspection photo 2, 3 July 2024

All 43 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

H M B Homes Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in One Beverly?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the One Beverly handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on One Beverly?
One Beverly was 73% built at the site inspection on 6 May 2026. The site has been inspected 6 times since July 2024. The Land Department took 43 site photos at its inspections.
Is One Beverly delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building One Beverly?
The registered developer is H M B Homes Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for One Beverly?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.