Off-plan projects in Dubai Sports City
21 projects in Dubai Sports City are under construction. On average they are 46% built. 8 have passed their registered completion date. The next one due is All Seasons Residence, in March 2027.
- Eden GardenLokhandwala Builders International Limited96%Due August 2022, passed
- Azizi GrandAzizi Developments82%Due February 2025, passed
- Sportz By DanubeDanube Properties Development80%Due March 2026, passed
- Mars ResidencesMars Star Real Estate Development80%Due March 2024, passed
- Binghatti HavenBinghatti Developers76%Due March 2026, passed
- Lime Light Twin TowersLime Light Real Estate Development71%Due June 2026, passed
- Urban Park ResidencesUrban Venture Real Estate Development68%Due April 2026, passed
- Mag 777Dng Property Development67%Due January 2026, passed
- The First Collection At Dubai Sports CityTfg International Real Estate Development66%Due November 2027
- Samana Golf ViewsSamana International Real Estate Development56%No date set
- SartoriaPinnacle A K S Real Estate Development51%Due October 2027
- Fairway Residences By PrescottPrescott Real Estate Development50%No date set
- Golf Residences By Prestige OnePrestige Golf Residences Real Estate Development44%Due February 2028
- The Community - Sports ArenaAqua Properties22%Due October 2027
- VegaAcube Real Estate Development20%Due May 2027
- Verde By VisionClear Vision Real Estate Development12%Due September 2027
- Aspirz By DanubeDanube Properties Development8.6%Due December 2028
- All Seasons ResidenceAbdulrahim Alzarooni Real Estate Development8.1%Due March 2027
- Aurelia ResidenceObject One Real Estate Development4.5%Due March 2028
- Antalya By KarmaKarma D S C Developers0.1%Due September 2028
- Hadley Heights 2Leos Development0%Due October 2027
Questions
How many off-plan projects are under construction in Dubai Sports City?
21 projects are under construction in Dubai Sports City, 46% built on average at the latest site inspections.
Which Dubai Sports City projects are due to finish next?
By registered completion date: All Seasons Residence (March 2027, 8.1% built), Vega (May 2027, 20% built) and Verde By Vision (September 2027, 12% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
How many Dubai Sports City projects are past their completion date?
8 of 21, among them Eden Garden, Mars Residences and Azizi Grand. A project counts as late once its registered completion date has passed before it reaches 100%.
Which developers are building in Dubai Sports City?
The developers with the most projects here are Danube Properties Development (2), out of 20 building in Dubai Sports City.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.