Mars Residences construction progress
Mars Residences in Dubai Sports City is 80% built at the Land Department inspection of August 2026. Developer Mars Star Real Estate Development. Completion registered for March 2024.
80%
Built, at the Land Department site inspection of 5 August 2026
31 months past its registered completion date
- Completion date (Land Department)
- March 2024
- Finish at recent pace
- July 2034
- Construction started
- April 2008
- Registered with the Land Department
- April 2008
- Developer
- Mars Star Real Estate Development
- Community
- Dubai Sports City
- Units
- 554
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- مارس ريزيدنسس
- Land Department project number
- 556
- Land Department site inspections
- 13
Schedule
Mars Residences was registered to complete in March 2024, 31 months ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around July 2034.
Site inspections
5 August 2026
80%+0.6 pts
31 March 2026
79%+1.2 pts
11 November 2025
78%+2.2 pts
15 July 2025
76%+0.2 pts
21 March 2025
76%+5.5 pts
30 July 2024
70%+5.1 pts
19 March 2024
65%+4.5 pts
6 November 2023
61%+0.5 pts
16 May 2023
60%+6.5 pts
18 January 2023
53%+3.3 pts
Context
Dubai Sports City has 21 projects under construction, 44% built on average.
Own a unit in Mars Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Mars Residences be completed?
- The completion date registered with the Dubai Land Department is March 2024. At the pace of its recent inspections the site would reach 100% around July 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Mars Residences is built?
- 80%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 13 times since June 2012.
- Is Mars Residences delayed?
- Yes. Its registered completion date of March 2024 has passed and the Land Department still lists it as under construction.
- Who is building Mars Residences?
- The registered developer is Mars Star Real Estate Development.
- Which bank holds the escrow account for Mars Residences?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Samana Golf ViewsNearby in Dubai Sports City. 56%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
























.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)