Mars Residences construction progress

Mars Residences in Dubai Sports City is 80% built at the Land Department inspection of August 2026. Developer Mars Star Real Estate Development. Completion registered for March 2024.

80%

Built, at the Land Department site inspection of 5 August 2026

31 months past its registered completion date

Completion date (Land Department)
March 2024
Finish at recent pace
July 2034
Construction started
April 2008
Registered with the Land Department
April 2008
Developer
Mars Star Real Estate Development
Units
554
Escrow bank
Emirates Islamic Bank
Name in Arabic
مارس ريزيدنسس
Land Department project number
556
Land Department site inspections
13

Schedule

Mars Residences was registered to complete in March 2024, 31 months ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around July 2034.

0%25%50%75%100%20092013201720212025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

5 August 2026

80%+0.6 pts

  • Mars Residences construction site, Land Department inspection photo 1, 5 August 2026
  • Mars Residences construction site, Land Department inspection photo 2, 5 August 2026
  • Mars Residences construction site, Land Department inspection photo 3, 5 August 2026
  • Mars Residences construction site, Land Department inspection photo 4, 5 August 2026

31 March 2026

79%+1.2 pts

  • Mars Residences construction site, Land Department inspection photo 1, 31 March 2026
  • Mars Residences construction site, Land Department inspection photo 2, 31 March 2026
  • Mars Residences construction site, Land Department inspection photo 3, 31 March 2026
  • Mars Residences construction site, Land Department inspection photo 4, 31 March 2026

11 November 2025

78%+2.2 pts

  • Mars Residences construction site, Land Department inspection photo 1, 11 November 2025
  • Mars Residences construction site, Land Department inspection photo 2, 11 November 2025
  • Mars Residences construction site, Land Department inspection photo 3, 11 November 2025
  • Mars Residences construction site, Land Department inspection photo 4, 11 November 2025

15 July 2025

76%+0.2 pts

  • Mars Residences construction site, Land Department inspection photo 1, 15 July 2025
  • Mars Residences construction site, Land Department inspection photo 2, 15 July 2025
  • Mars Residences construction site, Land Department inspection photo 3, 15 July 2025
  • Mars Residences construction site, Land Department inspection photo 4, 15 July 2025

21 March 2025

76%+5.5 pts

  • Mars Residences construction site, Land Department inspection photo 1, 21 March 2025
  • Mars Residences construction site, Land Department inspection photo 2, 21 March 2025
  • Mars Residences construction site, Land Department inspection photo 3, 21 March 2025
  • Mars Residences construction site, Land Department inspection photo 4, 21 March 2025

30 July 2024

70%+5.1 pts

  • Mars Residences construction site, Land Department inspection photo 1, 30 July 2024
  • Mars Residences construction site, Land Department inspection photo 2, 30 July 2024
  • Mars Residences construction site, Land Department inspection photo 3, 30 July 2024
  • Mars Residences construction site, Land Department inspection photo 4, 30 July 2024

19 March 2024

65%+4.5 pts

  • Mars Residences construction site, Land Department inspection photo 1, 19 March 2024
  • Mars Residences construction site, Land Department inspection photo 2, 19 March 2024
  • Mars Residences construction site, Land Department inspection photo 3, 19 March 2024
  • Mars Residences construction site, Land Department inspection photo 4, 19 March 2024

6 November 2023

61%+0.5 pts

  • Mars Residences construction site, Land Department inspection photo 1, 6 November 2023
  • Mars Residences construction site, Land Department inspection photo 2, 6 November 2023
  • Mars Residences construction site, Land Department inspection photo 3, 6 November 2023
  • Mars Residences construction site, Land Department inspection photo 4, 6 November 2023

16 May 2023

60%+6.5 pts

  • Mars Residences construction site, Land Department inspection photo 1, 16 May 2023
  • Mars Residences construction site, Land Department inspection photo 2, 16 May 2023
  • Mars Residences construction site, Land Department inspection photo 3, 16 May 2023
  • Mars Residences construction site, Land Department inspection photo 4, 16 May 2023

18 January 2023

53%+3.3 pts

  • Mars Residences construction site, Land Department inspection photo 1, 18 January 2023
  • Mars Residences construction site, Land Department inspection photo 2, 18 January 2023
  • Mars Residences construction site, Land Department inspection photo 3, 18 January 2023
  • Mars Residences construction site, Land Department inspection photo 4, 18 January 2023

All 120 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 44% built on average.

Own a unit in Mars Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Mars Residences be completed?
The completion date registered with the Dubai Land Department is March 2024. At the pace of its recent inspections the site would reach 100% around July 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mars Residences is built?
80%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 13 times since June 2012.
Is Mars Residences delayed?
Yes. Its registered completion date of March 2024 has passed and the Land Department still lists it as under construction.
Who is building Mars Residences?
The registered developer is Mars Star Real Estate Development.
Which bank holds the escrow account for Mars Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.