Golf Residences By Prestige One construction progress

The registered completion date for Golf Residences By Prestige One in Dubai Sports City is February 2028. At the last site inspection, in August 2026, it was 36% built. The developer is Prestige Golf Residences Real Estate Development.

44%

Built, at the site inspection of 10 August 2026

Running behind its date

Registered completion date
February 2028
Finish at recent pace
August 2028
Construction started
December 2024
First registered
July 2024
Developer
Prestige Golf Residences Real Estate Development
Units
226
Escrow bank
Emirates NBD
Name in Arabic
جولف ريزيدنسز من بريستيج ون
Project number
3131
Site inspections
6

Schedule

Between September 2025 and August 2026 the site added about 2.6 points a month. At that rate it would finish around August 2028, more than three months after its registered date of February 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 August 2026

36%+11 pts

  • Golf Residences By Prestige One construction site, inspection photo 1, 10 August 2026
  • Golf Residences By Prestige One construction site, inspection photo 2, 10 August 2026
  • Golf Residences By Prestige One construction site, inspection photo 3, 10 August 2026
  • Golf Residences By Prestige One construction site, inspection photo 4, 10 August 2026

20 April 2026

25%+7.5 pts

  • Golf Residences By Prestige One construction site, inspection photo 1, 20 April 2026
  • Golf Residences By Prestige One construction site, inspection photo 2, 20 April 2026
  • Golf Residences By Prestige One construction site, inspection photo 3, 20 April 2026
  • Golf Residences By Prestige One construction site, inspection photo 4, 20 April 2026

29 January 2026

18%+10 pts

  • Golf Residences By Prestige One construction site, inspection photo 1, 29 January 2026
  • Golf Residences By Prestige One construction site, inspection photo 2, 29 January 2026
  • Golf Residences By Prestige One construction site, inspection photo 3, 29 January 2026
  • Golf Residences By Prestige One construction site, inspection photo 4, 29 January 2026

19 September 2025

7.5%+3.0 pts

  • Golf Residences By Prestige One construction site, inspection photo 1, 19 September 2025
  • Golf Residences By Prestige One construction site, inspection photo 2, 19 September 2025
  • Golf Residences By Prestige One construction site, inspection photo 3, 19 September 2025
  • Golf Residences By Prestige One construction site, inspection photo 4, 19 September 2025

2 April 2025

4.5%+4.5 pts

  • Golf Residences By Prestige One construction site, inspection photo 1, 2 April 2025
  • Golf Residences By Prestige One construction site, inspection photo 2, 2 April 2025
  • Golf Residences By Prestige One construction site, inspection photo 3, 2 April 2025
  • Golf Residences By Prestige One construction site, inspection photo 4, 2 April 2025

12 June 2024

0%

  • Golf Residences By Prestige One construction site, inspection photo 1, 12 June 2024
  • Golf Residences By Prestige One construction site, inspection photo 2, 12 June 2024

All 32 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Golf Residences By Prestige One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Golf Residences By Prestige One handover date?
The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Golf Residences By Prestige One?
Golf Residences By Prestige One was 44% built at the site inspection on 10 August 2026. The site has been inspected 6 times since June 2024. The Land Department took 32 site photos at its inspections.
Is Golf Residences By Prestige One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Golf Residences By Prestige One?
The registered developer is Prestige Golf Residences Real Estate Development.
Which bank holds the escrow account for Golf Residences By Prestige One?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.