Golf Residences By Prestige One construction progress
The registered completion date for Golf Residences By Prestige One in Dubai Sports City is February 2028. At the last site inspection, in August 2026, it was 36% built. The developer is Prestige Golf Residences Real Estate Development.
44%
Built, at the site inspection of 10 August 2026
Running behind its date
- Registered completion date
- February 2028
- Finish at recent pace
- August 2028
- Construction started
- December 2024
- First registered
- July 2024
- Developer
- Prestige Golf Residences Real Estate Development
- Community
- Dubai Sports City
- Units
- 226
- Escrow bank
- Emirates NBD
- Name in Arabic
- جولف ريزيدنسز من بريستيج ون
- Project number
- 3131
- Site inspections
- 6
Schedule
Between September 2025 and August 2026 the site added about 2.6 points a month. At that rate it would finish around August 2028, more than three months after its registered date of February 2028.
Site inspections
10 August 2026
36%+11 pts
20 April 2026
25%+7.5 pts
29 January 2026
18%+10 pts
19 September 2025
7.5%+3.0 pts
2 April 2025
4.5%+4.5 pts
12 June 2024
0%
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Own a unit in Golf Residences By Prestige One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Golf Residences By Prestige One handover date?
- The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Golf Residences By Prestige One?
- Golf Residences By Prestige One was 44% built at the site inspection on 10 August 2026. The site has been inspected 6 times since June 2024. The Land Department took 32 site photos at its inspections.
- Is Golf Residences By Prestige One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
- Who is building Golf Residences By Prestige One?
- The registered developer is Prestige Golf Residences Real Estate Development.
- Which bank holds the escrow account for Golf Residences By Prestige One?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)