Mag 777 construction progress
Mag 777 in Dubai Sports City was registered to complete in January 2026 and is still under construction. At the last site inspection, in July 2026, it was 67% built. The developer is Dng Property Development.
67%
Built, at the site inspection of 30 July 2026
10 months past its registered completion date
- Registered completion date
- January 2026
- Finish at recent pace
- April 2028
- Construction started
- November 2024
- First registered
- October 2024
- Developer
- Dng Property Development
- Community
- Dubai Sports City
- Units
- 266
- Escrow bank
- Emirates NBD
- Name in Arabic
- ماج 777
- Project number
- 3193
- Site inspections
- 5
Schedule
Mag 777 was registered to complete in January 2026, 10 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around April 2028.
Site inspections
30 July 2026
67%+8.6 pts
2 April 2026
59%+4.7 pts
19 November 2025
54%+3.1 pts
2 June 2025
51%+2.4 pts
19 August 2024
49%
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Own a unit in Mag 777?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mag 777 handover date?
- The registered completion date was January 2026, and the register still lists Mag 777 as under construction. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mag 777?
- Mag 777 was 67% built at the site inspection on 30 July 2026. The site has been inspected 5 times since August 2024. The Land Department took 40 site photos at its inspections.
- Is Mag 777 delayed?
- Yes. Its registered completion date of January 2026 has passed and the project is still listed as under construction.
- Who is building Mag 777?
- The registered developer is Dng Property Development.
- Which bank holds the escrow account for Mag 777?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.