Mag 777 construction progress

Mag 777 in Dubai Sports City is 67% built at the Land Department inspection of July 2026. Developer Dng Property Development. Completion registered for January 2026.

67%

Built, at the Land Department site inspection of 30 July 2026

9 months past its registered completion date

Completion date (Land Department)
January 2026
Finish at recent pace
April 2028
Construction started
November 2024
Registered with the Land Department
October 2024
Developer
Dng Property Development
Units
266
Escrow bank
Emirates NBD
Name in Arabic
ماج 777
Land Department project number
3193
Land Department site inspections
5

Schedule

Mag 777 was registered to complete in January 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around April 2028.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 July 2026

67%+8.6 pts

  • Mag 777 construction site, Land Department inspection photo 1, 30 July 2026
  • Mag 777 construction site, Land Department inspection photo 2, 30 July 2026
  • Mag 777 construction site, Land Department inspection photo 3, 30 July 2026
  • Mag 777 construction site, Land Department inspection photo 4, 30 July 2026

2 April 2026

59%+4.7 pts

  • Mag 777 construction site, Land Department inspection photo 1, 2 April 2026
  • Mag 777 construction site, Land Department inspection photo 2, 2 April 2026
  • Mag 777 construction site, Land Department inspection photo 3, 2 April 2026
  • Mag 777 construction site, Land Department inspection photo 4, 2 April 2026

19 November 2025

54%+3.1 pts

  • Mag 777 construction site, Land Department inspection photo 1, 19 November 2025
  • Mag 777 construction site, Land Department inspection photo 2, 19 November 2025
  • Mag 777 construction site, Land Department inspection photo 3, 19 November 2025
  • Mag 777 construction site, Land Department inspection photo 4, 19 November 2025

2 June 2025

51%+2.4 pts

  • Mag 777 construction site, Land Department inspection photo 1, 2 June 2025
  • Mag 777 construction site, Land Department inspection photo 2, 2 June 2025
  • Mag 777 construction site, Land Department inspection photo 3, 2 June 2025
  • Mag 777 construction site, Land Department inspection photo 4, 2 June 2025

19 August 2024

49%

  • Mag 777 construction site, Land Department inspection photo 1, 19 August 2024
  • Mag 777 construction site, Land Department inspection photo 2, 19 August 2024
  • Mag 777 construction site, Land Department inspection photo 3, 19 August 2024
  • Mag 777 construction site, Land Department inspection photo 4, 19 August 2024

All 40 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 44% built on average.

Own a unit in Mag 777?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Mag 777 be completed?
The completion date registered with the Dubai Land Department is January 2026. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mag 777 is built?
67%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 5 times since August 2024.
Is Mag 777 delayed?
Yes. Its registered completion date of January 2026 has passed and the Land Department still lists it as under construction.
Who is building Mag 777?
The registered developer is Dng Property Development.
Which bank holds the escrow account for Mag 777?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.