Mag 777 construction progress
Mag 777 in Dubai Sports City is 67% built at the Land Department inspection of July 2026. Developer Dng Property Development. Completion registered for January 2026.
67%
Built, at the Land Department site inspection of 30 July 2026
9 months past its registered completion date
- Completion date (Land Department)
- January 2026
- Finish at recent pace
- April 2028
- Construction started
- November 2024
- Registered with the Land Department
- October 2024
- Developer
- Dng Property Development
- Community
- Dubai Sports City
- Units
- 266
- Escrow bank
- Emirates NBD
- Name in Arabic
- ماج 777
- Land Department project number
- 3193
- Land Department site inspections
- 5
Schedule
Mag 777 was registered to complete in January 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around April 2028.
Site inspections
30 July 2026
67%+8.6 pts
2 April 2026
59%+4.7 pts
19 November 2025
54%+3.1 pts
2 June 2025
51%+2.4 pts
19 August 2024
49%
Context
Dubai Sports City has 21 projects under construction, 44% built on average.
Own a unit in Mag 777?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Mag 777 be completed?
- The completion date registered with the Dubai Land Department is January 2026. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Mag 777 is built?
- 67%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 5 times since August 2024.
- Is Mag 777 delayed?
- Yes. Its registered completion date of January 2026 has passed and the Land Department still lists it as under construction.
- Who is building Mag 777?
- The registered developer is Dng Property Development.
- Which bank holds the escrow account for Mag 777?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.