Eden Garden construction progress
Eden Garden in Dubai Sports City was registered to complete in August 2022 and is still under construction. At the last site inspection, in July 2023, it was 96% built. The developer is Lokhandwala Builders International Limited.
96%
Built, at the site inspection of 14 July 2023
51 months past its registered completion date
- Registered completion date
- August 2022
- Finish at recent pace
- February 2026
- Construction started
- May 2008
- First registered
- November 2008
- Developer
- Lokhandwala Builders International Limited
- Community
- Dubai Sports City
- Units
- 394
- Escrow bank
- Bank of Baroda
- Name in Arabic
- عدن جاردن
- Project number
- 510
- Site inspections
- 15
Schedule
Eden Garden was registered to complete in August 2022, 51 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around February 2026.
Site inspections
14 July 2023
96%+0.4 pts
3 April 2023
96%+0.5 pts
31 March 2022
95%+3.5 pts
20 June 2021
92%+4.7 pts
19 November 2020
87%+1.5 pts
27 January 2019
85%+10 pts
18 March 2018
75%+15 pts
17 May 2017
60%+2.6 pts
21 August 2016
58%+2.6 pts
21 January 2016
55%+3.1 pts
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Own a unit in Eden Garden?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Eden Garden handover date?
- The registered completion date was August 2022, and the register still lists Eden Garden as under construction. At the pace of its recent inspections the site would reach 100% around February 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Eden Garden?
- Eden Garden was 96% built at the site inspection on 14 July 2023. The site has been inspected 15 times since October 2013. The Land Department took 141 site photos at its inspections.
- Is Eden Garden delayed?
- Yes. Its registered completion date of August 2022 has passed and the project is still listed as under construction.
- Who is building Eden Garden?
- The registered developer is Lokhandwala Builders International Limited.
- Which bank holds the escrow account for Eden Garden?
- Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Samana Golf ViewsNearby in Dubai Sports City. 56%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)