Eden Garden construction progress
Eden Garden in Dubai Sports City is 96% built at the Land Department inspection of July 2023. Developer Lokhandwala Builders International Limited. Completion registered for August 2022.
96%
Built, at the Land Department site inspection of 14 July 2023
49 months past its registered completion date
- Completion date (Land Department)
- August 2022
- Finish at recent pace
- February 2026
- Construction started
- May 2008
- Registered with the Land Department
- November 2008
- Developer
- Lokhandwala Builders International Limited
- Community
- Dubai Sports City
- Units
- 394
- Escrow bank
- Bank of Baroda
- Name in Arabic
- عدن جاردن
- Land Department project number
- 510
- Land Department site inspections
- 15
Schedule
Eden Garden was registered to complete in August 2022, 49 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around February 2026.
Site inspections
14 July 2023
96%+0.4 pts
3 April 2023
96%+0.5 pts
31 March 2022
95%+3.5 pts
20 June 2021
92%+4.7 pts
19 November 2020
87%+1.5 pts
27 January 2019
85%+10 pts
18 March 2018
75%+15 pts
17 May 2017
60%+2.6 pts
21 August 2016
58%+2.6 pts
21 January 2016
55%+3.1 pts
Context
Dubai Sports City has 21 projects under construction, 44% built on average.
Own a unit in Eden Garden?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Eden Garden be completed?
- The completion date registered with the Dubai Land Department is August 2022. At the pace of its recent inspections the site would reach 100% around February 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Eden Garden is built?
- 96%, measured at the Land Department site inspection on 14 July 2023. The Land Department engineers have inspected the site 15 times since October 2013.
- Is Eden Garden delayed?
- Yes. Its registered completion date of August 2022 has passed and the Land Department still lists it as under construction.
- Who is building Eden Garden?
- The registered developer is Lokhandwala Builders International Limited.
- Which bank holds the escrow account for Eden Garden?
- Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Samana Golf ViewsNearby in Dubai Sports City. 56%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)