Aurelia Residence construction progress

The registered completion date for Aurelia Residence in Dubai Sports City is March 2028. At the last site inspection, in October 2026, it was 4.5% built. The developer is Object One Real Estate Development.

4.5%

Built, at the site inspection of 28 October 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
June 2084
Construction started
July 2025
First registered
August 2025
Units
280
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
أوريليا ريزيدنس
Project number
3768
Site inspections
5

Schedule

Between November 2025 and October 2026 the site added about 0.1 points a month. At that rate it would finish around June 2084, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

4.5%

  • Aurelia Residence construction site, inspection photo 1, 28 October 2026
  • Aurelia Residence construction site, inspection photo 2, 28 October 2026
  • Aurelia Residence construction site, inspection photo 3, 28 October 2026

15 July 2026

4.5%

  • Aurelia Residence construction site, inspection photo 1, 15 July 2026
  • Aurelia Residence construction site, inspection photo 2, 15 July 2026
  • Aurelia Residence construction site, inspection photo 3, 15 July 2026
  • Aurelia Residence construction site, inspection photo 4, 15 July 2026

17 April 2026

4.5%+1.5 pts

  • Aurelia Residence construction site, inspection photo 1, 17 April 2026
  • Aurelia Residence construction site, inspection photo 2, 17 April 2026
  • Aurelia Residence construction site, inspection photo 3, 17 April 2026
  • Aurelia Residence construction site, inspection photo 4, 17 April 2026

27 November 2025

2.9%+2.9 pts

  • Aurelia Residence construction site, inspection photo 1, 27 November 2025
  • Aurelia Residence construction site, inspection photo 2, 27 November 2025
  • Aurelia Residence construction site, inspection photo 3, 27 November 2025

19 June 2025

0%

  • Aurelia Residence construction site, inspection photo 1, 19 June 2025
  • Aurelia Residence construction site, inspection photo 2, 19 June 2025

All 17 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Aurelia Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Aurelia Residence handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2084. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Aurelia Residence?
Aurelia Residence was 4.5% built at the site inspection on 28 October 2026. The site has been inspected 5 times since June 2025. The Land Department took 17 site photos at its inspections.
Is Aurelia Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Aurelia Residence?
The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for Aurelia Residence?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.