All Seasons Residence construction progress

The registered completion date for All Seasons Residence in Dubai Sports City is March 2027. At the last site inspection, in April 2026, it was 8.1% built. The developer is Abdulrahim Alzarooni Real Estate Development.

8.1%

Built, at the site inspection of 20 April 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
August 2040
Construction started
October 2024
First registered
October 2024
Developer
Abdulrahim Alzarooni Real Estate Development
Units
286
Escrow bank
Emirates NBD
Name in Arabic
اول سيزونز ريزيدنس
Project number
2978
Site inspections
3

Schedule

Between August 2025 and April 2026 the site added about 0.5 points a month. At that rate it would finish around August 2040, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 April 2026

8.1%+4.4 pts

  • All Seasons Residence construction site, inspection photo 1, 20 April 2026
  • All Seasons Residence construction site, inspection photo 2, 20 April 2026
  • All Seasons Residence construction site, inspection photo 3, 20 April 2026
  • All Seasons Residence construction site, inspection photo 4, 20 April 2026

14 August 2025

3.7%+3.7 pts

  • All Seasons Residence construction site, inspection photo 1, 14 August 2025
  • All Seasons Residence construction site, inspection photo 2, 14 August 2025
  • All Seasons Residence construction site, inspection photo 3, 14 August 2025
  • All Seasons Residence construction site, inspection photo 4, 14 August 2025

25 March 2024

0%

  • All Seasons Residence construction site, inspection photo 1, 25 March 2024
  • All Seasons Residence construction site, inspection photo 2, 25 March 2024

All 11 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in All Seasons Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the All Seasons Residence handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on All Seasons Residence?
All Seasons Residence was 8.1% built at the site inspection on 20 April 2026. The site has been inspected 3 times since March 2024. The Land Department took 11 site photos at its inspections.
Is All Seasons Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building All Seasons Residence?
The registered developer is Abdulrahim Alzarooni Real Estate Development.
Which bank holds the escrow account for All Seasons Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.