All Seasons Residence construction progress
The registered completion date for All Seasons Residence in Dubai Sports City is March 2027. At the last site inspection, in April 2026, it was 8.1% built. The developer is Abdulrahim Alzarooni Real Estate Development.
8.1%
Built, at the site inspection of 20 April 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- August 2040
- Construction started
- October 2024
- First registered
- October 2024
- Developer
- Abdulrahim Alzarooni Real Estate Development
- Community
- Dubai Sports City
- Units
- 286
- Escrow bank
- Emirates NBD
- Name in Arabic
- اول سيزونز ريزيدنس
- Project number
- 2978
- Site inspections
- 3
Schedule
Between August 2025 and April 2026 the site added about 0.5 points a month. At that rate it would finish around August 2040, more than three months after its registered date of March 2027.
Site inspections
20 April 2026
8.1%+4.4 pts
14 August 2025
3.7%+3.7 pts
25 March 2024
0%
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Own a unit in All Seasons Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the All Seasons Residence handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on All Seasons Residence?
- All Seasons Residence was 8.1% built at the site inspection on 20 April 2026. The site has been inspected 3 times since March 2024. The Land Department took 11 site photos at its inspections.
- Is All Seasons Residence delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building All Seasons Residence?
- The registered developer is Abdulrahim Alzarooni Real Estate Development.
- Which bank holds the escrow account for All Seasons Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)