Sartoria construction progress
The registered completion date for Sartoria in Dubai Sports City is October 2027. At the last site inspection, in October 2026, it was 51% built. The developer is Pinnacle A K S Real Estate Development.
51%
Built, at the site inspection of 15 October 2026
Running behind its date
- Registered completion date
- October 2027
- Finish at recent pace
- August 2029
- Construction started
- July 2025
- First registered
- May 2026
- Developer
- Pinnacle A K S Real Estate Development
- Community
- Dubai Sports City
- Units
- 224
- Escrow bank
- Mashreq Bank
- Name in Arabic
- سارتوريا
- Project number
- 3853
- Site inspections
- 2
Schedule
Between April 2026 and October 2026 the site added about 1.4 points a month. At that rate it would finish around August 2029, more than three months after its registered date of October 2027.
Site inspections
15 October 2026
51%+7.9 pts
30 April 2026
43%
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Pinnacle A K S Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Sartoria?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sartoria handover date?
- The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sartoria?
- Sartoria was 51% built at the site inspection on 15 October 2026. The site has been inspected 2 times since April 2026. The Land Department took 17 site photos at its inspections.
- Is Sartoria delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
- Who is building Sartoria?
- The registered developer is Pinnacle A K S Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Sartoria?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vitalia By PinnacleAlso by Pinnacle A K S Real Estate Development. 21%, Due June 2026, passed.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.