Sartoria construction progress

The registered completion date for Sartoria in Dubai Sports City is October 2027. At the last site inspection, in October 2026, it was 51% built. The developer is Pinnacle A K S Real Estate Development.

51%

Built, at the site inspection of 15 October 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
August 2029
Construction started
July 2025
First registered
May 2026
Developer
Pinnacle A K S Real Estate Development
Units
224
Escrow bank
Mashreq Bank
Name in Arabic
سارتوريا
Project number
3853
Site inspections
2

Schedule

Between April 2026 and October 2026 the site added about 1.4 points a month. At that rate it would finish around August 2029, more than three months after its registered date of October 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

51%+7.9 pts

  • Sartoria construction site, inspection photo 1, 15 October 2026
  • Sartoria construction site, inspection photo 2, 15 October 2026
  • Sartoria construction site, inspection photo 3, 15 October 2026
  • Sartoria construction site, inspection photo 4, 15 October 2026

30 April 2026

43%

  • Sartoria construction site, inspection photo 1, 30 April 2026
  • Sartoria construction site, inspection photo 2, 30 April 2026
  • Sartoria construction site, inspection photo 3, 30 April 2026
  • Sartoria construction site, inspection photo 4, 30 April 2026

All 17 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Pinnacle A K S Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Sartoria?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sartoria handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sartoria?
Sartoria was 51% built at the site inspection on 15 October 2026. The site has been inspected 2 times since April 2026. The Land Department took 17 site photos at its inspections.
Is Sartoria delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Sartoria?
The registered developer is Pinnacle A K S Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Sartoria?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.