Lime Light Twin Towers construction progress
Lime Light Twin Towers in Dubai Sports City is 71% built at the Land Department inspection of April 2026. Developer Lime Light Real Estate Development. Completion registered for June 2026.
71%
Built, at the Land Department site inspection of 2 April 2026
3 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- July 2038
- Construction started
- February 2025
- Registered with the Land Department
- February 2025
- Developer
- Lime Light Real Estate Development
- Community
- Dubai Sports City
- Units
- 734
- Escrow bank
- Mashreq Bank
- Name in Arabic
- لايم لايت توين تاور
- Land Department project number
- 558
- Land Department site inspections
- 17
Schedule
Lime Light Twin Towers was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around July 2038.
Site inspections
2 April 2026
71%+0.8 pts
24 November 2025
70%
18 January 2021
70%+0.2 pts
16 August 2020
70%+1.4 pts
19 November 2019
69%+0.3 pts
21 February 2019
68%+0.6 pts
24 December 2018
68%+0.6 pts
16 July 2018
67%+2.0 pts
21 January 2018
65%+3.0 pts
5 September 2017
62%+1.0 pts
Context
Dubai Sports City has 21 projects under construction, 44% built on average.
Own a unit in Lime Light Twin Towers?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Lime Light Twin Towers be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around July 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Lime Light Twin Towers is built?
- 71%, measured at the Land Department site inspection on 2 April 2026. The Land Department engineers have inspected the site 17 times since July 2014.
- Is Lime Light Twin Towers delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Lime Light Twin Towers?
- The registered developer is Lime Light Real Estate Development.
- Which bank holds the escrow account for Lime Light Twin Towers?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Samana Golf ViewsNearby in Dubai Sports City. 56%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)