Skip to content

Lime Light Twin Towers construction progress

Lime Light Twin Towers in Dubai Sports City is 71% built at the Land Department inspection of April 2026. Developer Lime Light Real Estate Development. Completion registered for June 2026.

71%

Built, at the Land Department site inspection of 2 April 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
July 2038
Construction started
February 2025
Registered with the Land Department
February 2025
Developer
Lime Light Real Estate Development
Units
734
Escrow bank
Mashreq Bank
Name in Arabic
لايم لايت توين تاور
Land Department project number
558
Land Department site inspections
17

Schedule

Lime Light Twin Towers was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around July 2038.

0%25%50%75%100%2015201820212024
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

2 April 2026

71%+0.8 pts

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 2 April 2026
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 2 April 2026
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 2 April 2026
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 2 April 2026

24 November 2025

70%

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 24 November 2025
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 24 November 2025
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 24 November 2025
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 24 November 2025

18 January 2021

70%+0.2 pts

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 18 January 2021
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 18 January 2021
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 18 January 2021
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 18 January 2021

16 August 2020

70%+1.4 pts

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 16 August 2020
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 16 August 2020
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 16 August 2020
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 16 August 2020

19 November 2019

69%+0.3 pts

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 19 November 2019
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 19 November 2019
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 19 November 2019
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 19 November 2019

21 February 2019

68%+0.6 pts

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 21 February 2019
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 21 February 2019
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 21 February 2019
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 21 February 2019

24 December 2018

68%+0.6 pts

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 24 December 2018
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 24 December 2018
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 24 December 2018
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 24 December 2018

16 July 2018

67%+2.0 pts

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 16 July 2018
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 16 July 2018
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 16 July 2018
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 16 July 2018

21 January 2018

65%+3.0 pts

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 21 January 2018
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 21 January 2018
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 21 January 2018
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 21 January 2018

5 September 2017

62%+1.0 pts

  • Lime Light Twin Towers construction site, Land Department inspection photo 1, 5 September 2017
  • Lime Light Twin Towers construction site, Land Department inspection photo 2, 5 September 2017
  • Lime Light Twin Towers construction site, Land Department inspection photo 3, 5 September 2017
  • Lime Light Twin Towers construction site, Land Department inspection photo 4, 5 September 2017

All 162 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 44% built on average.

Own a unit in Lime Light Twin Towers?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Lime Light Twin Towers be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around July 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Lime Light Twin Towers is built?
71%, measured at the Land Department site inspection on 2 April 2026. The Land Department engineers have inspected the site 17 times since July 2014.
Is Lime Light Twin Towers delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Lime Light Twin Towers?
The registered developer is Lime Light Real Estate Development.
Which bank holds the escrow account for Lime Light Twin Towers?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.