Aspirz By Danube construction progress
The registered completion date for Aspirz By Danube in Dubai Sports City is December 2028. At the last site inspection, in October 2026, it was 8.6% built. The developer is Danube Properties Development.
8.6%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- August 2033
- Construction started
- November 2025
- First registered
- September 2025
- Developer
- Danube Properties Development
- Community
- Dubai Sports City
- Units
- 706
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- أسبايرز من دانوب
- Project number
- 3838
- Site inspections
- 4
Schedule
Between April 2026 and October 2026 the site added about 1.1 points a month. At that rate it would finish around August 2033, more than three months after its registered date of December 2028.
Site inspections
28 October 2026
8.6%+3.5 pts
30 July 2026
5.1%+4.0 pts
6 April 2026
1.1%+1.1 pts
4 September 2025
0%
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Aspirz By Danube?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Aspirz By Danube handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Aspirz By Danube?
- Aspirz By Danube was 8.6% built at the site inspection on 28 October 2026. The site has been inspected 4 times since September 2025. The Land Department took 15 site photos at its inspections.
- Is Aspirz By Danube delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Aspirz By Danube?
- The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Aspirz By Danube?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 92%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 66%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 65%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)