Samana Golf Views construction progress
No completion date is registered for Samana Golf Views in Dubai Sports City yet. At the last site inspection, in September 2026, it was 56% built. The developer is Samana International Real Estate Development.
56%
Built, at the site inspection of 29 September 2026
- Finish at recent pace
- September 2027
- Construction started
- January 2024
- First registered
- September 2023
- Community
- Dubai Sports City
- Units
- 243
- Escrow bank
- Emirates NBD
- Name in Arabic
- سامانا جولف فيوز
- Project number
- 2707
- Site inspections
- 7
Schedule
Since November 2025 Samana Golf Views has added about 3.9 points a month. At that rate the site reaches 100% around September 2027. No completion date is on record to compare it with.
Site inspections
29 September 2026
56%+21 pts
1 June 2026
35%+9.1 pts
27 January 2026
26%+10 pts
21 November 2025
16%+9.0 pts
25 July 2025
6.9%+0.9 pts
6 February 2025
6.0%+6.0 pts
6 July 2023
0%
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Golf Views?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Golf Views handover date?
- No completion date is on record for Samana Golf Views yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Samana Golf Views?
- Samana Golf Views was 56% built at the site inspection on 29 September 2026. The site has been inspected 7 times since July 2023. The Land Department took 37 site photos at its inspections.
- Who is building Samana Golf Views?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Golf Views?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosAlso by Samana International Real Estate Development. 91%, Due April 2026, passed.
- Samana Mykonos SignatureAlso by Samana International Real Estate Development. 86%, Due April 2026, passed.
- Samana Ivy GardensAlso by Samana International Real Estate Development. 41%.
- Samana PortofinoAlso by Samana International Real Estate Development. 60%.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)











