Urban Park Residences construction progress

Urban Park Residences in Dubai Sports City was registered to complete in April 2026 and is still under construction. At the last site inspection, in July 2026, it was 68% built. The developer is Urban Venture Real Estate Development.

68%

Built, at the site inspection of 30 July 2026

8 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
October 2027
Construction started
October 2024
First registered
January 2025
Developer
Urban Venture Real Estate Development
Units
187
Escrow bank
United Bank Limited
Name in Arabic
اوربان بارك ريزيدنسيز
Project number
3230
Site inspections
4

Schedule

Urban Park Residences was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 2.3 points a month. Kept at that rate, the site would reach 100% around October 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 July 2026

68%+22 pts

  • Urban Park Residences construction site, inspection photo 1, 30 July 2026
  • Urban Park Residences construction site, inspection photo 2, 30 July 2026
  • Urban Park Residences construction site, inspection photo 3, 30 July 2026
  • Urban Park Residences construction site, inspection photo 4, 30 July 2026

6 January 2026

46%+5.2 pts

  • Urban Park Residences construction site, inspection photo 1, 6 January 2026
  • Urban Park Residences construction site, inspection photo 2, 6 January 2026
  • Urban Park Residences construction site, inspection photo 3, 6 January 2026
  • Urban Park Residences construction site, inspection photo 4, 6 January 2026

8 August 2025

41%+5.4 pts

  • Urban Park Residences construction site, inspection photo 1, 8 August 2025
  • Urban Park Residences construction site, inspection photo 2, 8 August 2025
  • Urban Park Residences construction site, inspection photo 3, 8 August 2025
  • Urban Park Residences construction site, inspection photo 4, 8 August 2025

11 December 2024

35%

  • Urban Park Residences construction site, inspection photo 1, 11 December 2024
  • Urban Park Residences construction site, inspection photo 2, 11 December 2024
  • Urban Park Residences construction site, inspection photo 3, 11 December 2024
  • Urban Park Residences construction site, inspection photo 4, 11 December 2024

All 28 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Urban Park Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Urban Park Residences handover date?
The registered completion date was April 2026, and the register still lists Urban Park Residences as under construction. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Urban Park Residences?
Urban Park Residences was 68% built at the site inspection on 30 July 2026. The site has been inspected 4 times since December 2024. The Land Department took 28 site photos at its inspections.
Is Urban Park Residences delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Urban Park Residences?
The registered developer is Urban Venture Real Estate Development.
Which bank holds the escrow account for Urban Park Residences?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.