Urban Park Residences construction progress
Urban Park Residences in Dubai Sports City was registered to complete in April 2026 and is still under construction. At the last site inspection, in July 2026, it was 68% built. The developer is Urban Venture Real Estate Development.
68%
Built, at the site inspection of 30 July 2026
8 months past its registered completion date
- Registered completion date
- April 2026
- Finish at recent pace
- October 2027
- Construction started
- October 2024
- First registered
- January 2025
- Developer
- Urban Venture Real Estate Development
- Community
- Dubai Sports City
- Units
- 187
- Escrow bank
- United Bank Limited
- Name in Arabic
- اوربان بارك ريزيدنسيز
- Project number
- 3230
- Site inspections
- 4
Schedule
Urban Park Residences was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 2.3 points a month. Kept at that rate, the site would reach 100% around October 2027.
Site inspections
30 July 2026
68%+22 pts
6 January 2026
46%+5.2 pts
8 August 2025
41%+5.4 pts
11 December 2024
35%
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Own a unit in Urban Park Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Urban Park Residences handover date?
- The registered completion date was April 2026, and the register still lists Urban Park Residences as under construction. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Urban Park Residences?
- Urban Park Residences was 68% built at the site inspection on 30 July 2026. The site has been inspected 4 times since December 2024. The Land Department took 28 site photos at its inspections.
- Is Urban Park Residences delayed?
- Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
- Who is building Urban Park Residences?
- The registered developer is Urban Venture Real Estate Development.
- Which bank holds the escrow account for Urban Park Residences?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.