The First Collection At Dubai Sports City construction progress
The registered completion date for The First Collection At Dubai Sports City in Dubai Sports City is November 2027. At the last site inspection, in September 2026, it was 66% built. The developer is Tfg International Real Estate Development.
66%
Built, at the site inspection of 21 September 2026
On pace for its date
- Registered completion date
- November 2027
- Finish at recent pace
- July 2027
- Construction started
- November 2023
- First registered
- March 2024
- Developer
- Tfg International Real Estate Development
- Community
- Dubai Sports City
- Units
- 478
- Escrow bank
- Arab Bank
- Name in Arabic
- ذا فيرست كوليكشن ات مدينة دبي الرياضية
- Project number
- 2745
- Site inspections
- 9
Schedule
Since October 2025 The First Collection At Dubai Sports City has added about 3.5 points a month. That puts 100% around July 2027, within three months of its registered completion date of November 2027.
Site inspections
21 September 2026
66%+6.3 pts
19 June 2026
59%+19 pts
3 March 2026
40%+12 pts
29 October 2025
28%+6.7 pts
20 June 2025
21%+6.2 pts
12 March 2025
15%+4.5 pts
4 December 2024
10%+5.4 pts
28 June 2024
5.1%+5.1 pts
2 November 2023
0%
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Own a unit in The First Collection At Dubai Sports City?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The First Collection At Dubai Sports City handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The First Collection At Dubai Sports City?
- The First Collection At Dubai Sports City was 66% built at the site inspection on 21 September 2026. The site has been inspected 9 times since November 2023. The Land Department took 51 site photos at its inspections.
- Is The First Collection At Dubai Sports City delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2027.
- Who is building The First Collection At Dubai Sports City?
- The registered developer is Tfg International Real Estate Development.
- Which bank holds the escrow account for The First Collection At Dubai Sports City?
- Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)










.png&w=3840&q=75)

.png&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)