Antalya By Karma construction progress

Antalya By Karma in Dubai Sports City is 0.1% built at the Land Department inspection of April 2026. Developer Karma D S C Developers. Completion registered for September 2028.

0.1%

Built, at the Land Department site inspection of 14 April 2026

Running behind its date

Completion date (Land Department)
September 2028
Finish at recent pace
March 3531
Construction started
October 2025
Registered with the Land Department
July 2025
Developer
Karma D S C Developers
Units
192
Escrow bank
First Abu Dhabi Bank
Name in Arabic
انطاليا من كارما
Land Department project number
3775
Land Department site inspections
2

Schedule

Between May 2025 and April 2026 the site added about 0.0 points a month. At that rate it would finish around March 3531, more than three months after the September 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 April 2026

0.1%+0.1 pts

  • Antalya By Karma construction site, Land Department inspection photo 1, 14 April 2026
  • Antalya By Karma construction site, Land Department inspection photo 2, 14 April 2026
  • Antalya By Karma construction site, Land Department inspection photo 3, 14 April 2026

19 May 2025

0%

  • Antalya By Karma construction site, Land Department inspection photo 1, 19 May 2025
  • Antalya By Karma construction site, Land Department inspection photo 2, 19 May 2025

All 5 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 44% built on average.

Own a unit in Antalya By Karma?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Antalya By Karma be completed?
The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around March 3531. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Antalya By Karma is built?
0.1%, measured at the Land Department site inspection on 14 April 2026. The Land Department engineers have inspected the site 2 times since May 2025.
Is Antalya By Karma delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Antalya By Karma?
The registered developer is Karma D S C Developers.
Which bank holds the escrow account for Antalya By Karma?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.