Vega construction progress

Vega in Dubai Sports City is 20% built at the Land Department inspection of August 2026. Developer Acube Real Estate Development. Completion registered for May 2027.

20%

Built, at the Land Department site inspection of 19 August 2026

Running behind its date

Completion date (Land Department)
May 2027
Finish at recent pace
March 2031
Construction started
January 2025
Registered with the Land Department
December 2024
Developer
Acube Real Estate Development
Units
129
Escrow bank
Dubai Islamic Bank
Name in Arabic
فيجا
Land Department project number
3414
Land Department site inspections
5

Schedule

Between December 2025 and August 2026 the site added about 1.5 points a month. At that rate it would finish around March 2031, more than three months after the May 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 August 2026

20%+5.2 pts

  • Vega construction site, Land Department inspection photo 1, 19 August 2026
  • Vega construction site, Land Department inspection photo 2, 19 August 2026
  • Vega construction site, Land Department inspection photo 3, 19 August 2026
  • Vega construction site, Land Department inspection photo 4, 19 August 2026

27 April 2026

15%+6.9 pts

  • Vega construction site, Land Department inspection photo 1, 27 April 2026
  • Vega construction site, Land Department inspection photo 2, 27 April 2026
  • Vega construction site, Land Department inspection photo 3, 27 April 2026
  • Vega construction site, Land Department inspection photo 4, 27 April 2026

9 December 2025

8.2%+5.4 pts

  • Vega construction site, Land Department inspection photo 1, 9 December 2025
  • Vega construction site, Land Department inspection photo 2, 9 December 2025
  • Vega construction site, Land Department inspection photo 3, 9 December 2025
  • Vega construction site, Land Department inspection photo 4, 9 December 2025

1 July 2025

2.8%+2.8 pts

  • Vega construction site, Land Department inspection photo 1, 1 July 2025
  • Vega construction site, Land Department inspection photo 2, 1 July 2025
  • Vega construction site, Land Department inspection photo 3, 1 July 2025
  • Vega construction site, Land Department inspection photo 4, 1 July 2025

21 November 2024

0%

  • Vega construction site, Land Department inspection photo 1, 21 November 2024
  • Vega construction site, Land Department inspection photo 2, 21 November 2024

All 26 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 44% built on average.

Acube Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vega?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vega be completed?
The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around March 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vega is built?
20%, measured at the Land Department site inspection on 19 August 2026. The Land Department engineers have inspected the site 5 times since November 2024.
Is Vega delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Vega?
The registered developer is Acube Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Vega?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.