Off-plan projects in International City Phase 3
21 projects in International City Phase 3 are under construction according to the Dubai Land Department. On average they are 30% built. 5 have passed their registered completion date. The next one due is Vio Residences, in December 2026.
- Mayflower ResidencesA J G Warsan Real Estate Development96%Due March 2026, passed
- Moonsa ResidencesDugasta Properties Development95%Due August 2025, passed
- The Maiden ResidenceTulip Althahabi Real Estate Development73%No date set
- Equiti TowerB N H Real Estate Developer70%Due August 2025, passed
- 08 Life ResidencesDeniz Properties65%Due May 2026, passed
- Tavora Residences By Jhk Heights Real Estate DevelopmentJhk Heights Real Estate Development61%No date set
- 27 East End Garden Residences By Mirha Homes Real Estate DevelopmentMirha Homes Real Estate Development40%Due January 2027
- Linden ResidencesBlack Soil Real Estate Development27%No date set
- Stellar Axis By Ajmal Estate DevelopersAjmal Estate Developers27%Due October 2026, passed
- Zenith ResidencesArt Of Amber Real Estate Development24%Due March 2028
- Sunlight HomesSunn And Sand Developers22%Due September 2027
- Sports View Residence 2 By Al Helal Al ZahabyAl Helal Al Zahaby Real Estate Development13%Due November 2029
- Ventana ResidencesZedor Real Estate Development6.7%No date set
- Vio ResidencesModelux Real Estate Development6.4%Due December 2026
- Elevia ResidencesValores Property Development3.0%Due June 2027
- Chapter 01 By Newbury DevelopmentsNewbury Real Estate Development2.4%Due October 2028
- Zyra Vista ResidencesLaraix Developers2.1%Due March 2027
- Moonsa Residences 2Dugasta Properties Development1.0%No date set
- NestAndi Real Estate Development0.8%Due April 2027
- Elevia Residences IiiValores Wbay Property Development0%Due July 2027
- Kyomi ResidenceAnax Developments0%No date set
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.