Off-plan projects in International City Phase 3
20 projects in International City Phase 3 are under construction. On average they are 28% built. 4 have passed their registered completion date. The next one due is Tavora Residences By Jhk Heights Real Estate Development, in December 2026.
- Mayflower ResidencesA J G Warsan Real Estate Development96%Due March 2026, passed
- Tavora Residences By Jhk Heights Real Estate DevelopmentJhk Heights Real Estate Development86%Due December 2026
- 08 Life ResidencesDeniz Properties78%Due May 2026, passed
- The Maiden ResidenceTulip Althahabi Real Estate Development73%Due December 2025, passed
- 27 East End Garden Residences By Mirha Homes Real Estate DevelopmentMirha Homes Real Estate Development58%Due January 2027
- Stellar Axis By Ajmal Estate DevelopersAjmal Estate Developers39%Due October 2026, passed
- Linden ResidencesBlack Soil Real Estate Development27%Due December 2027
- Sports View Residence 2 By Al Helal Al ZahabyAl Helal Al Zahaby Real Estate Development26%Due November 2029
- Zenith ResidencesArt Of Amber Real Estate Development24%Due March 2028
- Sunlight HomesSunn And Sand Developers22%Due September 2027
- Elevia ResidencesValores Property Development9.2%Due June 2027
- Ventana ResidencesZedor Real Estate Development6.7%Due February 2028
- Vio ResidencesModelux Real Estate Development6.4%Due December 2026
- Chapter 01 By Newbury DevelopmentsNewbury Real Estate Development2.4%Due October 2028
- Zyra Vista ResidencesLaraix Developers2.1%Due March 2027
- Chapter 02Newbury Chapter Real Estate Development2.1%Due December 2028
- Moonsa Residences 2Dugasta Properties Development1.0%Due December 2026
- NestAndi Real Estate Development0.8%Due April 2027
- Elevia Residences IIIValores Wbay Property Development0%Due July 2027
- Kyomi ResidenceAnax Developments0%Due January 2028
Questions
How many off-plan projects are under construction in International City Phase 3?
Which International City Phase 3 projects are due to finish next?
How many International City Phase 3 projects are past their completion date?
Which developers are building in International City Phase 3?
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.