The Maiden Residence construction progress

The Maiden Residence in International City Phase 3 was registered to complete in December 2025 and is still under construction. At the last site inspection, in May 2026, it was 73% built. The developer is Tulip Althahabi Real Estate Development.

73%

Built, at the site inspection of 14 May 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
October 2026
Construction started
January 2024
First registered
March 2025
Developer
Tulip Althahabi Real Estate Development
Units
71
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
ذا مايدن ريسدنس
Project number
2960
Site inspections
6

Schedule

The Maiden Residence was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 4.8 points a month. Kept at that rate, the site would reach 100% around October 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 May 2026

73%+1.7 pts

  • The Maiden Residence construction site, inspection photo 1, 14 May 2026
  • The Maiden Residence construction site, inspection photo 2, 14 May 2026
  • The Maiden Residence construction site, inspection photo 3, 14 May 2026
  • The Maiden Residence construction site, inspection photo 4, 14 May 2026

10 March 2026

71%+30 pts

  • The Maiden Residence construction site, inspection photo 1, 10 March 2026
  • The Maiden Residence construction site, inspection photo 2, 10 March 2026
  • The Maiden Residence construction site, inspection photo 3, 10 March 2026
  • The Maiden Residence construction site, inspection photo 4, 10 March 2026

7 November 2025

41%+17 pts

  • The Maiden Residence construction site, inspection photo 1, 7 November 2025
  • The Maiden Residence construction site, inspection photo 2, 7 November 2025
  • The Maiden Residence construction site, inspection photo 3, 7 November 2025
  • The Maiden Residence construction site, inspection photo 4, 7 November 2025

8 July 2025

24%+11 pts

  • The Maiden Residence construction site, inspection photo 1, 8 July 2025
  • The Maiden Residence construction site, inspection photo 2, 8 July 2025
  • The Maiden Residence construction site, inspection photo 3, 8 July 2025
  • The Maiden Residence construction site, inspection photo 4, 8 July 2025

9 December 2024

12%+9.7 pts

  • The Maiden Residence construction site, inspection photo 1, 9 December 2024
  • The Maiden Residence construction site, inspection photo 2, 9 December 2024
  • The Maiden Residence construction site, inspection photo 3, 9 December 2024
  • The Maiden Residence construction site, inspection photo 4, 9 December 2024

22 August 2024

2.6%

  • The Maiden Residence construction site, inspection photo 1, 22 August 2024
  • The Maiden Residence construction site, inspection photo 2, 22 August 2024

All 36 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in The Maiden Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Maiden Residence handover date?
The registered completion date was December 2025, and the register still lists The Maiden Residence as under construction. At the pace of its recent inspections the site would reach 100% around October 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Maiden Residence?
The Maiden Residence was 73% built at the site inspection on 14 May 2026. The site has been inspected 6 times since August 2024. The Land Department took 36 site photos at its inspections.
Is The Maiden Residence delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building The Maiden Residence?
The registered developer is Tulip Althahabi Real Estate Development.
Which bank holds the escrow account for The Maiden Residence?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.