The Maiden Residence construction progress
The Maiden Residence in International City Phase 3 was registered to complete in December 2025 and is still under construction. At the last site inspection, in May 2026, it was 73% built. The developer is Tulip Althahabi Real Estate Development.
73%
Built, at the site inspection of 14 May 2026
11 months past its registered completion date
- Registered completion date
- December 2025
- Finish at recent pace
- October 2026
- Construction started
- January 2024
- First registered
- March 2025
- Developer
- Tulip Althahabi Real Estate Development
- Community
- International City Phase 3
- Units
- 71
- Escrow bank
- National Bank of Ras Al Khaimah
- Name in Arabic
- ذا مايدن ريسدنس
- Project number
- 2960
- Site inspections
- 6
Schedule
The Maiden Residence was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 4.8 points a month. Kept at that rate, the site would reach 100% around October 2026.
Site inspections
14 May 2026
73%+1.7 pts
10 March 2026
71%+30 pts
7 November 2025
41%+17 pts
8 July 2025
24%+11 pts
9 December 2024
12%+9.7 pts
22 August 2024
2.6%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Own a unit in The Maiden Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Maiden Residence handover date?
- The registered completion date was December 2025, and the register still lists The Maiden Residence as under construction. At the pace of its recent inspections the site would reach 100% around October 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Maiden Residence?
- The Maiden Residence was 73% built at the site inspection on 14 May 2026. The site has been inspected 6 times since August 2024. The Land Department took 36 site photos at its inspections.
- Is The Maiden Residence delayed?
- Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
- Who is building The Maiden Residence?
- The registered developer is Tulip Althahabi Real Estate Development.
- Which bank holds the escrow account for The Maiden Residence?
- National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- 27 East End Garden Residences By Mirha Homes Real Estate DevelopmentNearby in International City Phase 3. 58%, Due January 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)