Sports View Residence 2 By Al Helal Al Zahaby construction progress
Sports View Residence 2 By Al Helal Al Zahaby in International City Phase 3 is 13% built at the Land Department inspection of August 2026. Developer Al Helal Al Zahaby Real Estate Development. Completion registered for November 2029.
13%
Built, at the Land Department site inspection of 12 August 2026
On pace for its date
- Completion date (Land Department)
- November 2029
- Finish at recent pace
- November 2028
- Construction started
- November 2025
- Registered with the Land Department
- December 2025
- Community
- International City Phase 3
- Units
- 128
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- سبورتس فيو ريسيدنس 2 باي الهلال الذهبي
- Land Department project number
- 3836
- Land Department site inspections
- 3
Schedule
Since May 2026 Sports View Residence 2 By Al Helal Al Zahaby has added about 3.2 points a month. That puts 100% around November 2028, within three months of its registered completion date of November 2029.
Site inspections
12 August 2026
13%+10 pts
5 May 2026
3.0%+3.0 pts
16 June 2025
0%
Context
International City Phase 3 has 21 projects under construction, 30% built on average.
Al Helal Al Zahaby Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sports View Residence 2 By Al Helal Al Zahaby?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Sports View Residence 2 By Al Helal Al Zahaby be completed?
- The completion date registered with the Dubai Land Department is November 2029. At the pace of its recent inspections the site would reach 100% around November 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Sports View Residence 2 By Al Helal Al Zahaby is built?
- 13%, measured at the Land Department site inspection on 12 August 2026. The Land Department engineers have inspected the site 3 times since June 2025.
- Is Sports View Residence 2 By Al Helal Al Zahaby delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2029.
- Who is building Sports View Residence 2 By Al Helal Al Zahaby?
- The registered developer is Al Helal Al Zahaby Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Sports View Residence 2 By Al Helal Al Zahaby?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Forest City TowerAlso by Al Helal Al Zahaby Real Estate Development. 70%, Due April 2027.
- Oasis ResidencesAlso by Al Helal Al Zahaby Real Estate Development. 35%.
- Forest City Tower 2Also by Al Helal Al Zahaby Real Estate Development. 0%, Due June 2027.
- Moonsa ResidencesNearby in International City Phase 3. 95%, Due August 2025, passed.
- The Maiden ResidenceNearby in International City Phase 3. 73%.
- Linden ResidencesNearby in International City Phase 3. 27%.
- Equiti TowerNearby in International City Phase 3. 70%, Due August 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.