Vio Residences construction progress

The registered completion date for Vio Residences in International City Phase 3 is December 2026. At the last site inspection, in August 2026, it was 6.4% built. The developer is Modelux Real Estate Development.

6.4%

Built, at the site inspection of 3 August 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
October 2033
Construction started
January 2025
First registered
September 2025
Developer
Modelux Real Estate Development
Units
87
Escrow bank
Dubai Islamic Bank
Name in Arabic
فيو ريزيدنسز
Project number
3673
Site inspections
3

Schedule

Between March 2026 and August 2026 the site added about 1.1 points a month. At that rate it would finish around October 2033, more than three months after its registered date of December 2026.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 August 2026

6.4%+5.4 pts

  • Vio Residences construction site, inspection photo 1, 3 August 2026
  • Vio Residences construction site, inspection photo 2, 3 August 2026
  • Vio Residences construction site, inspection photo 3, 3 August 2026
  • Vio Residences construction site, inspection photo 4, 3 August 2026

2 March 2026

1.0%+1.0 pts

  • Vio Residences construction site, inspection photo 1, 2 March 2026
  • Vio Residences construction site, inspection photo 2, 2 March 2026
  • Vio Residences construction site, inspection photo 3, 2 March 2026
  • Vio Residences construction site, inspection photo 4, 2 March 2026

9 April 2025

0%

  • Vio Residences construction site, inspection photo 1, 9 April 2025

All 9 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in Vio Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vio Residences handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vio Residences?
Vio Residences was 6.4% built at the site inspection on 3 August 2026. The site has been inspected 3 times since April 2025. The Land Department took 9 site photos at its inspections.
Is Vio Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Vio Residences?
The registered developer is Modelux Real Estate Development.
Which bank holds the escrow account for Vio Residences?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.