Vio Residences construction progress
The registered completion date for Vio Residences in International City Phase 3 is December 2026. At the last site inspection, in August 2026, it was 6.4% built. The developer is Modelux Real Estate Development.
6.4%
Built, at the site inspection of 3 August 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- October 2033
- Construction started
- January 2025
- First registered
- September 2025
- Developer
- Modelux Real Estate Development
- Community
- International City Phase 3
- Units
- 87
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- فيو ريزيدنسز
- Project number
- 3673
- Site inspections
- 3
Schedule
Between March 2026 and August 2026 the site added about 1.1 points a month. At that rate it would finish around October 2033, more than three months after its registered date of December 2026.
Site inspections
3 August 2026
6.4%+5.4 pts
2 March 2026
1.0%+1.0 pts
9 April 2025
0%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Own a unit in Vio Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Vio Residences handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Vio Residences?
- Vio Residences was 6.4% built at the site inspection on 3 August 2026. The site has been inspected 3 times since April 2025. The Land Department took 9 site photos at its inspections.
- Is Vio Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Vio Residences?
- The registered developer is Modelux Real Estate Development.
- Which bank holds the escrow account for Vio Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)