Vio Residences construction progress

Vio Residences in International City Phase 3 is 6.4% built at the Land Department inspection of August 2026. Developer Modelux Real Estate Development. Completion registered for December 2026.

6.4%

Built, at the Land Department site inspection of 3 August 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
October 2033
Construction started
January 2025
Registered with the Land Department
September 2025
Developer
Modelux Real Estate Development
Units
87
Escrow bank
Dubai Islamic Bank
Name in Arabic
فيو ريزيدنسز
Land Department project number
3673
Land Department site inspections
3

Schedule

Between March 2026 and August 2026 the site added about 1.1 points a month. At that rate it would finish around October 2033, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 August 2026

6.4%+5.4 pts

  • Vio Residences construction site, Land Department inspection photo 1, 3 August 2026
  • Vio Residences construction site, Land Department inspection photo 2, 3 August 2026
  • Vio Residences construction site, Land Department inspection photo 3, 3 August 2026
  • Vio Residences construction site, Land Department inspection photo 4, 3 August 2026

2 March 2026

1.0%+1.0 pts

  • Vio Residences construction site, Land Department inspection photo 1, 2 March 2026
  • Vio Residences construction site, Land Department inspection photo 2, 2 March 2026
  • Vio Residences construction site, Land Department inspection photo 3, 2 March 2026
  • Vio Residences construction site, Land Department inspection photo 4, 2 March 2026

9 April 2025

0%

  • Vio Residences construction site, Land Department inspection photo 1, 9 April 2025

All 9 site photos, by inspection date

Context

International City Phase 3 has 21 projects under construction, 30% built on average.

Own a unit in Vio Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vio Residences be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around October 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vio Residences is built?
6.4%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 3 times since April 2025.
Is Vio Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Vio Residences?
The registered developer is Modelux Real Estate Development.
Which bank holds the escrow account for Vio Residences?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.