Vio Residences construction progress
Vio Residences in International City Phase 3 is 6.4% built at the Land Department inspection of August 2026. Developer Modelux Real Estate Development. Completion registered for December 2026.
6.4%
Built, at the Land Department site inspection of 3 August 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- October 2033
- Construction started
- January 2025
- Registered with the Land Department
- September 2025
- Developer
- Modelux Real Estate Development
- Community
- International City Phase 3
- Units
- 87
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- فيو ريزيدنسز
- Land Department project number
- 3673
- Land Department site inspections
- 3
Schedule
Between March 2026 and August 2026 the site added about 1.1 points a month. At that rate it would finish around October 2033, more than three months after the December 2026 date registered with the Land Department.
Site inspections
3 August 2026
6.4%+5.4 pts
2 March 2026
1.0%+1.0 pts
9 April 2025
0%
Context
International City Phase 3 has 21 projects under construction, 30% built on average.
Own a unit in Vio Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Vio Residences be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around October 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Vio Residences is built?
- 6.4%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 3 times since April 2025.
- Is Vio Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Vio Residences?
- The registered developer is Modelux Real Estate Development.
- Which bank holds the escrow account for Vio Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Moonsa ResidencesNearby in International City Phase 3. 95%, Due August 2025, passed.
- The Maiden ResidenceNearby in International City Phase 3. 73%.
- Linden ResidencesNearby in International City Phase 3. 27%.
- Equiti TowerNearby in International City Phase 3. 70%, Due August 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)